Buildings & civic facilities · job 186-23-000001
Comprehensive Balance Development & Improvements to Multipurpose Building & Construction of Kitchen in Tank Bund Road, Tavarekere, additional improvements to Kuvempu Park Multipurpose Building & other Improvements to Parks & Playground in BTM Layout Assmebly Constituency (Package 10)
₹13.82 Crcontract / award · inferred
₹15.63 Crpaid, gross
5bills
08 Apr 2026last activity
- Planned
- Contracted
- Work documented
- Paid
- Completed
- Physical evidence
no tender found for these bills
This project was reviewed for the investigation cases and set aside: why.
Signals — patterns worth a closer look, not findings of wrongdoing
-
notice 1 bill(s) registered after the final bill confirmed
Final bill registered 2025-07-01; later non-final bills exist. [source]
-
notice Billed quantity above plan (3 items) inferred
_ Rupees One the legs. Maintenance free self-greased SKF ball each Lakh(s) Forty — planned 2 nos (Schedule B), bill form total up to date 4 (+100%); _ Rupees Two handles. Bearings; Maintenance-free self-greased SKF each Borla a. — planned 2 (Schedule B), bill form total up to date 4 (+100%); hitty handles. Bearings: Maintenance-free self-greased SKF_ each = Fi e-thousand — planned 2 nos (Schedule B), bill form total up to date 4 (+100%). Possible explanations: approved deviation or supplementary schedule, site conditions, an OCR misread on the plan side (each row passed quantity × rate = amount). [source] [source]
-
notice Quantity above plan with no variation document visible (3 items) inferred
_ Rupees One the legs. Maintenance free self-greased SKF ball each Lakh(s) Forty — planned 2 nos (Schedule B), bill form total up to date 4 (+100%); _ Rupees Two handles. Bearings; Maintenance-free self-greased SKF each Borla a. — planned 2 (Schedule B), bill form total up to date 4 (+100%); hitty handles. Bearings: Maintenance-free self-greased SKF_ each = Fi e-thousand — planned 2 nos (Schedule B), bill form total up to date 4 (+100%). No supplementary Schedule B, deviation statement, work slip or revised-estimate attachment is listed for this job in IFMS (it may exist on paper). [source] [source]
-
info Fine / penalty deducted from a bill confirmed
IFMS deductions: fine ₹41,800. Penalties usually relate to delay or quality; their reason is not in the public record. [source]
- info 3 bills paid on the same day (2026-04-08) confirmed
-
info Same placeholder file uploaded as evidence on several works confirmed
The same file (md5 a3a7ee1247…; Completion Certificate) is attached to bills of 3 works: 151-20-000102, 151-21-000002. A placeholder means the real record is missing. [source]
Related: 151-20-000102, 151-21-000002
1 · What was planned
Work
Comprehensive Balance Development & Improvements to Multipurpose Building & Construction of Kitchen in Tank Bund Road, Tavarekere, additional improvements to Kuvempu Park Multipurpose Building & other Improvements to Parks & Playground in BTM Layout Assmebly Constituency (Package 10)
confirmed [1]
Where
Tavarekere
inferred
Place names read from the work description text
Estimated cost
Unknown
unknown
No estimate published for this work in the sources used
Tender published
Unknown
unknown
No tender found or matched for this work
Time allowed
Unknown
unknown
No tender document found or matched
2 · Who got the work (contract)
Contractor
Contractor identity
C0027 · DASARADHA RAMI REDDY
confirmed [1] [2]
Resolved contractor C0027 “DASARADHA RAMI REDDY”; identifiers: IFMS:012376; name variants joined by: single name variant.
Contract value
₹13.82 Cr
inferred [1]
Contract / tender price stated in the Work Order (read by OCR from the scanned document)
3 · Work documented
Bills recorded
Work documents
Quantities: planned vs billed
10 of 30 planned items compared (Schedule B (contract BOQ) vs bill abstracts); median quantity difference -16%
inferred [1] [2] +4
Planned quantities (Schedule B / estimate) against billed (bill abstracts) and measured (typed MB sheets) quantities. Only rows where quantity × rate = amount on the scanned page are used; handwritten MB pages are left unread. Never overrides IFMS amounts.
↳ from a tender matched to these bills (none confidence) — why
4 · Money paid
Paid (nett)
Paid vs contract
First payment
Last payment
Fines / withheld / recoveries
Bill → payment (median days)
Approval remarks
34 remark(s); e.g. 2025-07-11: “Approved by SC(F)/ZC/CE/CAO — Approved.”
confirmed [1]
Remarks written by officials in the IFMS approval chain
11 Apr 2025cumulative payments08 Apr 2026
5 · Completion
Status
Completed (final bill)
inferred [1]
Inferred from the final bill: BBMP raises the final bill when measurement of the completed work is recorded
Work started
Unknown
unknown
Actual start date is not published
Expected completion
Unknown
unknown
Stipulated period of completion not found in any public record
Final bill
Completed on
Unknown
unknown
Final bill does not carry an end date
6 · Physical evidence
Site photos
Satellite imagery
Inconclusive
inferred [1] [2]
Manual comparison of satellite captures 2024-01-18 (WV02, 0.5 m) → 2026-01-08 (WV02, 0.5 m) around the geocoded point: The point is the Tavarekere locality node. The multipurpose building on Tank Bund Road cannot be identified in dense housing. Experimental: location is geocoded from place names in the description, captures are not perfectly co-registered, and small works (drains, footpaths) are below what 0.3–0.6 m imagery can show.
Quantities: Schedule B vs billed — read from scanned documents; only rows where quantity × rate = amount are used
| Item | Unit | Planned | Rate | Billed / measured | Difference | Basis | Confidence | Source |
|---|---|---|---|---|---|---|---|---|
| art of sand Thousand Two underneath to come up in between joints, final sqm Hundred Twenty | sqm | 4,315.03 | ₹1,224 | 1,979.11 | -54% | bill form total up to date | medium | [1] [2] |
| Six as per the Directions of Engineer In Charge of The Thousand One Work Cum HundredSixAnd | cum | 658.67 | ₹6,107 | 451.40 | -32% | bill abstracts (sum of read bills) | medium | [1] [2] |
| cost of steel weacl an piety reinforcement & formwork shall be paid separately) xed baleen | — | 540.46 | ₹6,042 | — | — | not billed / not read | medium | [1] |
| Lakh(s) Forty length of not less tham Sft. Moulder FRP slides are non. each eve Thousand! | nos | 15.00 | ₹1,45,000 | — | — | not billed / not read | high | [1] |
| rs with lousane: H wkou paver/grader in ait bees / base course on well) Cum Hundred Ninety | cum | 728.17 | ₹2,696 | 366.67 | -50% | bill abstracts (sum of read bills) | medium | [1] [2] |
| of %. Thousand Seven The tile shall be laid on mm wide T - section flanges Hundred Eighty | — | 762.50 | ₹1,783 | — | — | not billed / not read | medium | [1] |
| mming, Thousand Four consolidating and dressing complete.complete as per cum Hundred Fifty | cum | 515.26 | ₹2,452 | — | — | not billed / not read | high | [1] |
| ead for Thousand One fixing of glass shall be of size 20mm x mm. Windows 54m Hundred Fifty | — | 134.37 | ₹8,155 | — | — | not billed / not read | medium | [1] |
| other Thousand Four appurtenances required to complete the work as per Cum Hundred Ninety | cum | 73.08 | ₹8,495 | 61.15 | -16% | bill form total up to date | high | [1] [2] |
| y No Rupees Two can be done. It gives cardiovascular benefits pramotes each _Lakh(s) Fifty | nos | 2.00 | ₹2,58,000 | — | — | not billed / not read | high | [1] |
| making through Thousand Four jointing with sealant, making holes 25mmx12mm Hundred Ninety | — | 144.48 | ₹3,496 | 53.00 | -63% | bill abstracts (sum of read bills) | medium | [1] [2] |
| for M the _ Rupees Two handles. Bearings; Maintenance-free self-greased SKF each Borla a. | — | 2.00 | ₹2,48,000 | 4.00 | +100% | bill form total up to date | medium | [1] [2] |
| e. vats) Thitty handles. Bearings: Maintenance-free self-greased SKF_ each = Fi e-thousand | nos | 2.00 | ₹2,35,000 | 4.00 | +100% | bill form total up to date | high | [1] [2] |
| -Greased SKF ball Rupees One bearings. Scope of Delivery: completely pre- cach pom Seventy | — | 2.00 | ₹1,72,000 | — | — | not billed / not read | medium | [1] |
| per fo = entae I —= the specification and as per the Directions of Engineer m TwoAndPaise | m | 3,060.05 | ₹92 | 2,782.43 | -9% | bill form total up to date | medium | [1] [2] |
| d low to, _ Rupees One the legs. Maintenance free self-greased SKF ball each Lakh(s) Forty | nos | 2.00 | ₹1,40,000 | 4.00 | +100% | bill form total up to date | high | [1] [2] |
| ion and as per Ru F ; the Directions of Engineer In Charge of The Work each Thousand Gedy. | nos | 5.00 | ₹46,000 | — | — | not billed / not read | high | [1] |
| ding, Hundred Thirty including cost of materials, labour, curing complete as Two And Paise | — | 241.23 | ₹432 | 113.69 | -53% | bill abstracts (sum of read bills) | medium | [1] [2] |
| , power, Thousand Six loss should< % of lamp Wage, short circuit & open each Hundred Sixty | nos | 30.00 | ₹1,665 | — | — | not billed / not read | high | [1] |
| a wood /PVC upees Six f -ound block. complete for each outlet. Long point Point sajapomyee | nos | 70.00 | ₹610 | — | — | not billed / not read | high | [1] |
| jointing o __ Rupees Three \pipes and fangs with one step solvent cement. & Hundred Fifty | — | 120.00 | ₹356 | — | — | not billed / not read | medium | [1] |
| floor as Thousand Six required and disposal of the debris with lead upto Hundred Seventy) | — | 12.00 | ₹1,673 | — | — | not billed / not read | medium | [1] |
| nting Thousand Nine fittings and brackets, cutting and making good the) Pan Hundred Eighty | — | 5.00 | ₹3,983 | — | — | not billed / not read | medium | [1] |
| ther Thousand Seven appurtenances required to complete the work as per) Cum Hundred Eighty | cum | 1.94 | ₹7,787 | — | — | not billed / not read | high | [1] |
| h plate as per 1s Rupees Ninety i and IS .6A One Way Switchcomplete as per' Nine And Paise | — | 132.00 | ₹99 | — | — | not billed / not read | medium | [1] |
| C Hundred Fifty cound block. complete for each outlet. Two Out let ina . Point Five sea oa | nos | 16.00 | ₹756 | — | — | not billed / not read | high | [1] |
| roup-A Rupees Seventy , Amps Bakelite Ceiling Rosecomplete as per the No And Paise Ninety. | nos | 100.00 | ₹71 | — | — | not billed / not read | high | [1] |
| ate as per IS Rupees One g3 and IS .6A Three Way socketcomplete as per each Hundred Eighty | nos | 28.00 | ₹182 | — | — | not billed / not read | high | [1] |
| as per h Hundred Thi the Directions of Engineer In Charge of The Work eae And Paise Nidef | — | 20.00 | ₹231 | — | — | not billed / not read | medium | [1] |
| m conduit Rupees Thirteen using necessary machine screws. 110mmcomplete as And Paise Fifty | — | 30.00 | ₹14 | — | — | not billed / not read | medium | [1] |
Running-bill figures show progress at that bill, not final quantities. Comparisons are inferred; see methodology.
Timeline
Bills & payments (BBMP)
| Bill type | Bill reg. (BR) | Work order | Gross | Nett | Payment | Payee | Source |
|---|---|---|---|---|---|---|---|
| Running | 000015 · 16 May 2024 | — | ₹10,03,54,000 | ₹9,68,09,586 | RTGS 002586 11 Apr 2025 | DASARADHA RAMI REDDY | BBMP Work Orders and Payments 2025-26 (243-ward regime) · row 15 |
| Running | 000051 · 26 Aug 2024 | — | ₹4,96,15,000 | ₹4,48,01,002 | RTGS 003392 11 Jul 2025 | DASARADHA RAMI REDDY | BBMP Work Orders and Payments 2025-26 (243-ward regime) · row 366 |
| First and Final | 000011 · 01 Jul 2025 | — | ₹4,95,000 | ₹4,45,500 | RTGS 000037 08 Apr 2026 | H & P CONSULTANTS | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
| Running | 000015 · 01 Jul 2025 | — | ₹12,15,000 | ₹10,93,500 | RTGS 000039 08 Apr 2026 | STRUCTIAL CONSULTANT | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
| Running | 000077 · 07 Nov 2025 | — | ₹45,79,600 | ₹43,62,009 | RTGS 000061 08 Apr 2026 | DASARADHA RAMI REDDY | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
Original system: BBMP Works Bill Public View / IFMS (account.bbmpgov.in). Linked files are public exports of that data on OpenCity.
Why this is a Koramangala project
Booked to Koramangala ward (186 under the 243-ward map)