Buildings & civic facilities · job 151-21-000002
Construction and Improvements of Multipurpose buildings, Development of Play ground and parks in BTM Layout Constituency Annexure-6 Sl No 2
—contract / award · unknown
₹12.24 Crpaid, gross
4bills
17 Jul 2026last activity
- Planned
- Contracted
- Work documented
- Paid
- Completed
- Physical evidence
no tender found for these bills
This project was reviewed for the investigation cases and set aside: why.
Signals — patterns worth a closer look, not findings of wrongdoing
- notice Blank / placeholder file used as a site photo confirmed
-
notice Billed quantity above plan (1 item) inferred
d tipper to site, laying in uniform layers with paver in sub- Cum Twenty One And — planned 302.7 (Schedule B), bill form total up to date 385.11 (+27%). Possible explanations: approved deviation or supplementary schedule, site conditions, an OCR misread on the plan side (each row passed quantity × rate = amount). [source] [source]
-
info Fine / penalty deducted from a bill confirmed
IFMS deductions: fine ₹63,200. Penalties usually relate to delay or quality; their reason is not in the public record. [source]
- info Bill paid in part (release % below 100) confirmed
-
info Same placeholder file uploaded as evidence on several works confirmed
The same file (md5 a3a7ee1247…; Completion Certificate) is attached to bills of 3 works: 151-20-000102, 186-23-000001. A placeholder means the real record is missing. [source]
Related: 151-20-000102, 186-23-000001 -
info Same placeholder file uploaded as evidence on several works confirmed
The same file (md5 4a81885c98…; Completion Certificate, Photo - After Work, Photo - Before Work, Photo - Work In Progress) is attached to bills of 3 works: 148-17-000002, 151-19-000056. A placeholder means the real record is missing. [source]
Related: 148-17-000002, 151-19-000056
1 · What was planned
Work
Construction and Improvements of Multipurpose buildings, Development of Play ground and parks in BTM Layout Constituency Annexure-6 Sl No 2
confirmed [1]
Where
Unknown
unknown
No place name could be read from the description
Estimated cost
Unknown
unknown
No estimate published for this work in the sources used
Tender published
Unknown
unknown
No tender found or matched for this work
Time allowed
Unknown
unknown
No tender document found or matched
2 · Who got the work (contract)
Contractor
Contractor identity
C0027 · DASARADHA RAMI REDDY
confirmed [1] [2] +1
Resolved contractor C0027 “DASARADHA RAMI REDDY”; identifiers: IFMS:012376; name variants joined by: single name variant.
Contract value
Unknown
unknown
Contract (work-order) value is not published in BBMP bill data and no awarded tender was matched
3 · Work documented
Bills recorded
Work documents
Quantities: planned vs billed
8 of 44 planned items compared (Schedule B (contract BOQ) vs bill abstracts); median quantity difference -35%
inferred [1] [2] +4
Planned quantities (Schedule B / estimate) against billed (bill abstracts) and measured (typed MB sheets) quantities. Only rows where quantity × rate = amount on the scanned page are used; handwritten MB pages are left unread. Never overrides IFMS amounts.
↳ from a tender matched to these bills (none confidence) — why
4 · Money paid
Paid (nett)
First payment
Last payment
Partial release
Fines / withheld / recoveries
Unpaid / pending bills
Bill → payment (median days)
Approval remarks
39 remark(s); e.g. 2026-07-22: “Verified and CBR Generated by EE”
confirmed [1]
Remarks written by officials in the IFMS approval chain
20 Feb 2024cumulative payments17 Jul 2026
5 · Completion
Status
Running bill only (no final bill found)
inferred [1]
Latest bill is a part (running) bill; no final bill in the published data
Work started
Unknown
unknown
Actual start date is not published
Expected completion
Unknown
unknown
Stipulated period of completion not found in any public record
Completed on
Unknown
unknown
No final bill found
6 · Physical evidence
Site photos
Quantities: Schedule B vs billed — read from scanned documents; only rows where quantity × rate = amount are used
| Item | Unit | Planned | Rate | Billed / measured | Difference | Basis | Confidence | Source |
|---|---|---|---|---|---|---|---|---|
| d Five Bx means of expansion bolts to the brick pillars with necesary Sqm tr indred Ninety | — | 5,109.42 | ₹9,595 | 1,863.76 | -64% | bill abstracts (sum of read bills) | medium | [1] [2] |
| es Two B the excavated stuff to a distance not exceeding 50m and lift up Cum Hundred Sixty | — | 6,709.95 | ₹267 | 2,890.18 | -57% | bill abstracts (sum of read bills) | medium | [1] [2] |
| Thousand One having tons compaction force thereby forcing part of sand Sqm Hundred Twenty | — | 1,349.30 | ₹1,123 | 872.96 | -35% | bill form total up to date | medium | [1] [2] |
| usand Four slab making through jointing with sealant, making holes 25mm Sqm Hundred Ninety | — | 449.53 | ₹2,492 | — | — | not billed / not read | medium | [1] |
| undation, includi scene ms. thick an well compacted’ for oundation, including Gym Hun Nine | — | 242.88 | ₹3,210 | — | — | not billed / not read | medium | [1] |
| ousand Two all works in foundation for footings, pedastals, retaining walls, Cum ee pwenty | — | 122.88 | ₹6,222 | — | — | not billed / not read | medium | [1] |
| usand Two sub soil treatment including watering ramming with all lead and Cum Hundred Five | — | 320.83 | ₹2,205 | — | — | not billed / not read | medium | [1] |
| d Twen dressing the bottom and sides of pits and trenches, stacking the Cum , nd Paise Ses | — | 2,031.55 | ₹320 | 701.36 | -66% | bill abstracts (sum of read bills) | medium | [1] [2] |
| ent mortar Hundred : mis finished with flush pointing using white cement, Sqm Eighteen And | — | 490.64 | ₹1,319 | — | — | not billed / not read | medium | [1] |
| by Thousand tipper to site, laying in uniform layers with paver in sub- Cum Twenty One And | — | 302.70 | ₹2,021 | 385.11 | +27% | bill form total up to date | medium | [1] [2] |
| nd Three cms high, bond stones at two m. apart in each course including Cum Hundred Ninety | — | 171.81 | ₹3,397 | — | — | not billed / not read | medium | [1] |
| hree » along with pipes and poles as per the directions of the engineer pity Hundred Three | — | 1,775.30 | ₹303 | 2,047.00 | +15% | bill form total up to date | medium | [1] [2] |
| peesTwo super set paint over a coat of protective Zinc chromate yellow No. — Lakh(s) Sixty | — | 2.00 | ₹2,60,000 | — | — | not billed / not read | medium | [1] |
| ll basketball Rupees Two rims (hoops) are inches ( cm) in diameter, The inner’ Lakh(s) Two | — | 2.00 | ₹2,02,000 | — | — | not billed / not read | medium | [1] |
| usand Sixty aaa proof course and pointed with cement mortar : mix with red Sqm , ang paise | — | 233.16 | ₹1,067 | — | — | not billed / not read | medium | [1] |
| main beam is mtrs x _ and height mtrs. The Nos of cost iron-heads. Four footing No. See ae | — | 3.00 | ₹46,000 | — | — | not billed / not read | medium | [1] |
| venty _ disposal of unserviceable material and stacking the serviceable Cum Five And Paise | — | 280.35 | ₹376 | — | — | not billed / not read | medium | [1] |
| ding Hundred One cutting steel sections and welding the same to required pattern And Paise | — | 949.84 | ₹102 | — | — | not billed / not read | medium | [1] |
| Rupees Nine including all lead and lift charges as per the direction of Mtr Hundred Forty | — | 101.00 | ₹942 | — | — | not billed / not read | medium | [1] |
| venty footings, bases of columns for mass concrete including cost of all Sqm Six And Paise | sqm | 340.56 | ₹276 | — | — | not billed / not read | high | [1] |
| ng Frondred f works with sand of approved quality, providing and removing Sqm Nineteen And | — | 425.53 | ₹219 | — | — | not billed / not read | medium | [1] |
| ift . SS ly transportation ete., and any other incidental charges and as per Sqm aa te aad | — | 390.48 | ₹235 | 24.50 | -94% | bill abstracts (sum of read bills) | medium | [1] [2] |
| ___ Thousand either side & Smm thick 20mm wide PVC sheet as gap insert for Sqm Twenty Nine | — | 15.12 | ₹3,029 | — | — | not billed / not read | medium | [1] |
| eventy scaffolding wherever necessary, sorting the dismantled material, Cum Five And Paise | — | 95.17 | ₹376 | 148.89 | +56% | bill abstracts (sum of read bills) | medium | [1] [2] |
| and DG Thousand Four clamps, overflow arrangements with special and 25mm Each Hundred Six | — | 5.00 | ₹5,406 | — | — | not billed / not read | medium | [1] |
| as Thousand Six per drawing and panels of 25mm thick including cost of Sqm Hundred Seventy | — | 4.20 | ₹4,676 | — | — | not billed / not read | medium | [1] |
| % and G.L. clamps painting of fittings and brackets, cutting and Unit . Hundred Forty —_- | — | 4.00 | ₹4,543 | — | — | not billed / not read | medium | [1] |
| Faure ms Clips, making good the wall, cuiling and Noor including cost Cl Mir hes poe peed | — | 30.00 | ₹491 | — | — | not billed / not read | medium | [1] |
| ars, seat ree post and struts, square rectangular polygon in plan including Sqm ae a A eal | sqm | 29.16 | ₹497 | — | — | not billed / not read | high | [1] |
| ngements as wy with special and 25mm mosquito proof coupling of approved Pan Hundred Seven | — | 3.00 | ₹4,608 | — | — | not billed / not read | medium | [1] |
| housand Five eae painting of fittings and brackets, cutting and making Unit Hundred Eighty | — | 2.00 | ₹3,587 | — | — | not billed / not read | medium | [1] |
| nag uh = jsides and bottom, filling back the excavated earth to the extent Cum Seventy Two | — | 108.99 | ₹57 | — | — | not billed / not read | medium | [1] |
| upees One jearth on which apron is to be laid, surrounding of pipes and Sqm re d Pa Pitan | sqm | 38.99 | ₹116 | — | — | not billed / not read | high | [1] |
| dred Fifty HOM with all leads complete as per specifications, mm dia) Each Seven And Paise | nos | 12.00 | ₹257 | — | — | not billed / not read | medium | [1] |
| _ breaks in floor including cost of all materials, labour complete as Sqm +hree And Paise | — | 3.11 | ₹824 | — | — | not billed / not read | medium | [1] |
| y including cost of all materials, cost of labour and scaffolding etc., Sqm Five And Paise | — | 19.43 | ₹85 | — | — | not billed / not read | medium | [1] |
| housand Three us curve indicator ONOFF energy cross- with short circuit Each Hundred Sixty | nos | 1.00 | ₹1,369 | — | — | not billed / not read | medium | [1] |
| ty brushing to give an even shade after cleaning oil, grease, dirt, Sqm , And Paise Ninety | — | 11.88 | ₹71 | — | — | not billed / not read | medium | [1] |
| y Six brushing to give an even shade after cleaning oil, grease, dirt Sqm And Paise Fifty. | — | 11.88 | ₹67 | — | — | not billed / not read | medium | [1] |
| a Thirty , necessary clamping arrangements for UG cable of .1KV class Mtr ‘Eight And Paise | — | 2.00 | ₹338 | — | — | not billed / not read | medium | [1] |
Running-bill figures show progress at that bill, not final quantities. Comparisons are inferred; see methodology.
Timeline
Bills & payments (BBMP)
| Bill type | Bill reg. (BR) | Work order | Gross | Nett | Payment | Payee | Source |
|---|---|---|---|---|---|---|---|
| Running | 000102 · 31 Mar 2023 | — | ₹3,93,47,300 | ₹3,58,46,984 | RTGS 001289 20 Feb 2024 | DASARADHA RAMI REDDY | BBMP Work Orders 2023-24 · row 5876 |
| Running | 000046 · 21 Nov 2023 | — | ₹4,35,58,600 | ₹4,17,68,836 | RTGS 001896 20 Aug 2024 | DASARADHA RAMI REDDY | BBMP Work Orders and Payments 2024-25 (198-ward regime) · row 4572 |
| Running | 000064 · 31 Jan 2024 | — | ₹2,99,79,100 | ₹2,89,13,380 | RTGS 001922 20 Aug 2024 | DASARADHA RAMI REDDY | BBMP Work Orders and Payments 2024-25 (198-ward regime) · row 4573 |
| Running | 000039 · 28 Aug 2025 | — | ₹95,20,175 | ₹86,53,192 | RTGS 000044 17 Jul 2026 | DASARADHA RAMI REDDY | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
Original system: BBMP Works Bill Public View / IFMS (account.bbmpgov.in). Linked files are public exports of that data on OpenCity.
Why this is a Koramangala project
Booked to Koramangala ward (151 under the 198-ward map)