Bengaluru Public Works Explorer Koramangala

← All works

Buildings & civic facilities · job 151-21-000002

Construction and Improvements of Multipurpose buildings, Development of Play ground and parks in BTM Layout Constituency Annexure-6 Sl No 2

Running bill only (no final bill found) Bruhat Bengaluru Mahanagara Palike
—contract / award · unknown
₹12.24 Crpaid, gross
4bills
17 Jul 2026last activity
  1. Planned
  2. Contracted
  3. Work documented
  4. Paid
  5. Completed
  6. Physical evidence
no tender found for these bills

This project was reviewed for the investigation cases and set aside: why.

Signals — patterns worth a closer look, not findings of wrongdoing

  • notice Blank / placeholder file used as a site photo confirmed
    3 photo slot(s) filled with a blank / placeholder file. Bills require before/during/after photos; a placeholder means the photo record for this work is missing. [source] [source]
  • notice Billed quantity above plan (1 item) inferred
    d tipper to site, laying in uniform layers with paver in sub- Cum Twenty One And — planned 302.7 (Schedule B), bill form total up to date 385.11 (+27%). Possible explanations: approved deviation or supplementary schedule, site conditions, an OCR misread on the plan side (each row passed quantity × rate = amount). [source] [source]
  • info Fine / penalty deducted from a bill confirmed
    IFMS deductions: fine ₹63,200. Penalties usually relate to delay or quality; their reason is not in the public record. [source]
  • info Bill paid in part (release % below 100) confirmed
    3 bill(s) released partly (75%, 75%, 75%). BBMP releases bills in tranches when funds are short; the balance may follow later. [source] [source]
  • info Same placeholder file uploaded as evidence on several works confirmed
    The same file (md5 a3a7ee1247…; Completion Certificate) is attached to bills of 3 works: 151-20-000102, 186-23-000001. A placeholder means the real record is missing. [source]
    Related: 151-20-000102, 186-23-000001
  • info Same placeholder file uploaded as evidence on several works confirmed
    The same file (md5 4a81885c98…; Completion Certificate, Photo - After Work, Photo - Before Work, Photo - Work In Progress) is attached to bills of 3 works: 148-17-000002, 151-19-000056. A placeholder means the real record is missing. [source]
    Related: 148-17-000002, 151-19-000056

1 · What was planned

Work
Construction and Improvements of Multipurpose buildings, Development of Play ground and parks in BTM Layout Constituency Annexure-6 Sl No 2 confirmed [1]
Where
Unknown unknown
No place name could be read from the description
Ward
151 (198-ward map) confirmed [1] [2]
Ward the bills are booked to
Estimated cost
Unknown unknown
No estimate published for this work in the sources used
Tender published
Unknown unknown
No tender found or matched for this work
Time allowed
Unknown unknown
No tender document found or matched

2 · Who got the work (contract)

Contractor
DASARADHA RAMI REDDY confirmed [1] [2] +1
Payee with the largest billed amount under this job number
Contractor identity
C0027 · DASARADHA RAMI REDDY confirmed [1] [2] +1
Resolved contractor C0027 “DASARADHA RAMI REDDY”; identifiers: IFMS:012376; name variants joined by: single name variant.
Contract value
Unknown unknown
Contract (work-order) value is not published in BBMP bill data and no awarded tender was matched

3 · Work documented

Bills recorded
4 running, 0 final paid/registered; 2 unpaid confirmed [1] [2] +2
Bill types recorded in BBMP IFMS for this job's work bills
Work documents
Completion Certificate ×4 (3 placeholder); Inspection Report ×5; M.B ×5; Quality Certificate ×4; Road History ×4 confirmed [1] [2] +2
Documents attached to the bills in IFMS (their presence is recorded; contents are not verified)
Quantities: planned vs billed
8 of 44 planned items compared (Schedule B (contract BOQ) vs bill abstracts); median quantity difference -35% inferred [1] [2] +4
Planned quantities (Schedule B / estimate) against billed (bill abstracts) and measured (typed MB sheets) quantities. Only rows where quantity × rate = amount on the scanned page are used; handwritten MB pages are left unread. Never overrides IFMS amounts.
↳ from a tender matched to these bills (none confidence) — why

4 · Money paid

Paid (gross)
₹12.24 Cr confirmed [1] [2] +1
Sum of 4 bill(s) under the job number
Paid (nett)
₹11.52 Cr confirmed [1] [2] +1
Gross minus statutory deductions (tax, security deposit, etc.)
Bills
4 confirmed [1] [2] +1
Unique bills after merging duplicates across exports
First payment
20 Feb 2024 confirmed [1]
Earliest payment (CBR/RTGS) date
Last payment
17 Jul 2026 confirmed [1]
Latest payment (CBR/RTGS) date
Partial release
3 bill(s) released partly (75%, 75%, 75%) confirmed [1] [2] +1
Release percentage recorded in IFMS (BBMP pays bills in tranches when funds are short)
Fines / withheld / recoveries
fine ₹63,200 confirmed [1]
Deduction heads recorded in IFMS across this job's bills
Unpaid / pending bills
2 bill(s) not paid (₹21,043,354); at: SC(F) / CE ×1, EE (Acts. Supdt.) ×1 confirmed [1] [2]
Bills present in IFMS without an RTGS payment (drafts or bills awaiting approval); not counted as paid
Bill → payment (median days)
323 confirmed [1]
Median days from bill registration to RTGS payment over 4 IFMS bill(s)
Approval remarks
39 remark(s); e.g. 2026-07-22: “Verified and CBR Generated by EE” confirmed [1]
Remarks written by officials in the IFMS approval chain
20 Feb 2024cumulative payments17 Jul 2026

5 · Completion

Status
Running bill only (no final bill found) inferred [1]
Latest bill is a part (running) bill; no final bill in the published data
Work started
Unknown unknown
Actual start date is not published
Expected completion
Unknown unknown
Stipulated period of completion not found in any public record
Completed on
Unknown unknown
No final bill found

6 · Physical evidence

Site photos
9 site photo(s) attached (before / during / after as labelled); no GPS on any photo checked confirmed [1] [2] +2
Photos attached to the bills in IFMS (type as labelled by the uploader)
Placeholder photos
3 photo slot(s) filled with a blank / placeholder file confirmed [1] [2] +1
Photo attachments whose file name says empty/blank or whose file is a few KB

Quantities: Schedule B vs billed — read from scanned documents; only rows where quantity × rate = amount are used

ItemUnitPlannedRateBilled / measuredDifferenceBasisConfidenceSource
d Five Bx means of expansion bolts to the brick pillars with necesary Sqm tr indred Ninety— 5,109.42 ₹9,595 1,863.76 -64% bill abstracts (sum of read bills) medium [1] [2]
es Two B the excavated stuff to a distance not exceeding 50m and lift up Cum Hundred Sixty— 6,709.95 ₹267 2,890.18 -57% bill abstracts (sum of read bills) medium [1] [2]
Thousand One having tons compaction force thereby forcing part of sand Sqm Hundred Twenty— 1,349.30 ₹1,123 872.96 -35% bill form total up to date medium [1] [2]
usand Four slab making through jointing with sealant, making holes 25mm Sqm Hundred Ninety— 449.53 ₹2,492 — — not billed / not read medium [1]
undation, includi scene ms. thick an well compacted’ for oundation, including Gym Hun Nine— 242.88 ₹3,210 — — not billed / not read medium [1]
ousand Two all works in foundation for footings, pedastals, retaining walls, Cum ee pwenty— 122.88 ₹6,222 — — not billed / not read medium [1]
usand Two sub soil treatment including watering ramming with all lead and Cum Hundred Five— 320.83 ₹2,205 — — not billed / not read medium [1]
d Twen dressing the bottom and sides of pits and trenches, stacking the Cum , nd Paise Ses— 2,031.55 ₹320 701.36 -66% bill abstracts (sum of read bills) medium [1] [2]
ent mortar Hundred : mis finished with flush pointing using white cement, Sqm Eighteen And— 490.64 ₹1,319 — — not billed / not read medium [1]
by Thousand tipper to site, laying in uniform layers with paver in sub- Cum Twenty One And— 302.70 ₹2,021 385.11 +27% bill form total up to date medium [1] [2]
nd Three cms high, bond stones at two m. apart in each course including Cum Hundred Ninety— 171.81 ₹3,397 — — not billed / not read medium [1]
hree » along with pipes and poles as per the directions of the engineer pity Hundred Three— 1,775.30 ₹303 2,047.00 +15% bill form total up to date medium [1] [2]
peesTwo super set paint over a coat of protective Zinc chromate yellow No. — Lakh(s) Sixty— 2.00 ₹2,60,000 — — not billed / not read medium [1]
ll basketball Rupees Two rims (hoops) are inches ( cm) in diameter, The inner’ Lakh(s) Two— 2.00 ₹2,02,000 — — not billed / not read medium [1]
usand Sixty aaa proof course and pointed with cement mortar : mix with red Sqm , ang paise— 233.16 ₹1,067 — — not billed / not read medium [1]
main beam is mtrs x _ and height mtrs. The Nos of cost iron-heads. Four footing No. See ae— 3.00 ₹46,000 — — not billed / not read medium [1]
venty _ disposal of unserviceable material and stacking the serviceable Cum Five And Paise— 280.35 ₹376 — — not billed / not read medium [1]
ding Hundred One cutting steel sections and welding the same to required pattern And Paise— 949.84 ₹102 — — not billed / not read medium [1]
Rupees Nine including all lead and lift charges as per the direction of Mtr Hundred Forty— 101.00 ₹942 — — not billed / not read medium [1]
venty footings, bases of columns for mass concrete including cost of all Sqm Six And Paisesqm 340.56 ₹276 — — not billed / not read high [1]
ng Frondred f works with sand of approved quality, providing and removing Sqm Nineteen And— 425.53 ₹219 — — not billed / not read medium [1]
ift . SS ly transportation ete., and any other incidental charges and as per Sqm aa te aad— 390.48 ₹235 24.50 -94% bill abstracts (sum of read bills) medium [1] [2]
___ Thousand either side & Smm thick 20mm wide PVC sheet as gap insert for Sqm Twenty Nine— 15.12 ₹3,029 — — not billed / not read medium [1]
eventy scaffolding wherever necessary, sorting the dismantled material, Cum Five And Paise— 95.17 ₹376 148.89 +56% bill abstracts (sum of read bills) medium [1] [2]
and DG Thousand Four clamps, overflow arrangements with special and 25mm Each Hundred Six— 5.00 ₹5,406 — — not billed / not read medium [1]
as Thousand Six per drawing and panels of 25mm thick including cost of Sqm Hundred Seventy— 4.20 ₹4,676 — — not billed / not read medium [1]
% and G.L. clamps painting of fittings and brackets, cutting and Unit . Hundred Forty —_-— 4.00 ₹4,543 — — not billed / not read medium [1]
Faure ms Clips, making good the wall, cuiling and Noor including cost Cl Mir hes poe peed— 30.00 ₹491 — — not billed / not read medium [1]
ars, seat ree post and struts, square rectangular polygon in plan including Sqm ae a A ealsqm 29.16 ₹497 — — not billed / not read high [1]
ngements as wy with special and 25mm mosquito proof coupling of approved Pan Hundred Seven— 3.00 ₹4,608 — — not billed / not read medium [1]
housand Five eae painting of fittings and brackets, cutting and making Unit Hundred Eighty— 2.00 ₹3,587 — — not billed / not read medium [1]
nag uh = jsides and bottom, filling back the excavated earth to the extent Cum Seventy Two— 108.99 ₹57 — — not billed / not read medium [1]
upees One jearth on which apron is to be laid, surrounding of pipes and Sqm re d Pa Pitansqm 38.99 ₹116 — — not billed / not read high [1]
dred Fifty HOM with all leads complete as per specifications, mm dia) Each Seven And Paisenos 12.00 ₹257 — — not billed / not read medium [1]
_ breaks in floor including cost of all materials, labour complete as Sqm +hree And Paise— 3.11 ₹824 — — not billed / not read medium [1]
y including cost of all materials, cost of labour and scaffolding etc., Sqm Five And Paise— 19.43 ₹85 — — not billed / not read medium [1]
housand Three us curve indicator ONOFF energy cross- with short circuit Each Hundred Sixtynos 1.00 ₹1,369 — — not billed / not read medium [1]
ty brushing to give an even shade after cleaning oil, grease, dirt, Sqm , And Paise Ninety— 11.88 ₹71 — — not billed / not read medium [1]
y Six brushing to give an even shade after cleaning oil, grease, dirt Sqm And Paise Fifty.— 11.88 ₹67 — — not billed / not read medium [1]
a Thirty , necessary clamping arrangements for UG cable of .1KV class Mtr ‘Eight And Paise— 2.00 ₹338 — — not billed / not read medium [1]

Running-bill figures show progress at that bill, not final quantities. Comparisons are inferred; see methodology.

Timeline

  1. 20 Feb 2024 Running bill ₹3.93 Cr paid source
  2. 20 Aug 2024 Running bill ₹4.36 Cr paid source
  3. 20 Aug 2024 Running bill ₹3.00 Cr paid source
  4. 17 Jul 2026 Running bill ₹95.20 L paid source

Bills & payments (BBMP)

Bill typeBill reg. (BR)Work orderGrossNettPaymentPayeeSource
Running 000102 · 31 Mar 2023 — ₹3,93,47,300₹3,58,46,984 RTGS 001289 20 Feb 2024 DASARADHA RAMI REDDY BBMP Work Orders 2023-24 · row 5876
Running 000046 · 21 Nov 2023 — ₹4,35,58,600₹4,17,68,836 RTGS 001896 20 Aug 2024 DASARADHA RAMI REDDY BBMP Work Orders and Payments 2024-25 (198-ward regime) · row 4572
Running 000064 · 31 Jan 2024 — ₹2,99,79,100₹2,89,13,380 RTGS 001922 20 Aug 2024 DASARADHA RAMI REDDY BBMP Work Orders and Payments 2024-25 (198-ward regime) · row 4573
Running 000039 · 28 Aug 2025 — ₹95,20,175₹86,53,192 RTGS 000044 17 Jul 2026 DASARADHA RAMI REDDY BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None

Original system: BBMP Works Bill Public View / IFMS (account.bbmpgov.in). Linked files are public exports of that data on OpenCity.

Why this is a Koramangala project

Booked to Koramangala ward (151 under the 198-ward map)