Roads, drains & footpaths (combined) · job 152-20-000049
Providing Asphalting improvements to roads, drains and footpath and other development works in Koramangala K R Garden Koramangala Village 14th main Jakkansandra Balajinagara 6th main Maruthinagar roads, Sriramappa layout Dodamuthappa layout, Tavarekere, Madiwala, Mico layout SFHS Layout, MKES college and surrounding areas in ward no 151,173,152,172,and 176 (Old Annexure-2 New Sl No 78 ,79, 80, 81, 82, 83, 84, 70, 73, 74, 75, 76, 77
—contract / award · unknown
₹10.06 Crpaid, gross
7bills
29 Mar 2023last activity
- Planned
- Contracted
- Work documented
- Paid
- Completed
- Physical evidence
no tender found for these bills
This project was reviewed for the investigation cases and set aside: why.
Signals — patterns worth a closer look, not findings of wrongdoing
- notice Blank / placeholder file used as a site photo confirmed
-
notice 4 bill(s) registered after the final bill confirmed
Final bill registered 2021-08-13; later non-final bills exist. [source]
-
notice Identical Completion Certificate attached to another job number confirmed
The same file (md5 6e99fdc0ec…; Completion Certificate) is attached to bills of 2 works: 151-20-000080. Could be one contract booked under two job numbers, or a wrong upload — worth checking. [source]
Related: 151-20-000080 - info 4 bills paid on the same day (2022-04-27) confirmed
1 · What was planned
Work
Providing Asphalting improvements to roads, drains and footpath and other development works in Koramangala K R Garden Koramangala Village 14th main Jakkansandra Balajinagara 6th main Maruthinagar roads, Sriramappa layout Dodamuthappa layout, Tavarekere, Madiwala, Mico layout SFHS Layout, MKES college and surrounding areas in ward no 151,173,152,172,and 176 (Old Annexure-2 New Sl No 78 ,79, 80, 81, 82, 83, 84, 70, 73, 74, 75, 76, 77
confirmed [1]
Where
14th Main; 6th Main; Tavarekere; Madiwala
inferred
Place names read from the work description text
Estimated cost
Unknown
unknown
No estimate published for this work in the sources used
Tender published
Unknown
unknown
No tender found or matched for this work
Time allowed
270 days (~9 months)
inferred [1]
Time of completion in the Agreement (read by OCR from the scanned document)
2 · Who got the work (contract)
Contractor
Contractor identity
C0042 · V M R CONSTRUCTION
confirmed [1] [2]
Resolved contractor C0042 “V M R CONSTRUCTION”; identifiers: no official identifier in the data; name variants joined by: single name variant.
Contract value
Unknown
unknown
Contract (work-order) value is not published in BBMP bill data and no awarded tender was matched
Work order
EE/BTM/WO/ 06 /2021-22 dated ?
inferred [1]
Work order reference in the Work Order (read by OCR from the scanned document)
3 · Work documented
Bills recorded
Work documents
Quantities: planned vs billed
8 of 25 planned items compared (Schedule B (contract BOQ) vs bill abstracts); median quantity difference -57%
inferred [1] [2] +4
Planned quantities (Schedule B / estimate) against billed (bill abstracts) and measured (typed MB sheets) quantities. Only rows where quantity × rate = amount on the scanned page are used; handwritten MB pages are left unread. Never overrides IFMS amounts.
↳ from a tender matched to these bills (none confidence) — why
4 · Money paid
Paid (nett)
First payment
Last payment
Unpaid / pending bills
Bill → payment (median days)
Approval remarks
78 remark(s); e.g. 2022-01-19: “Rejected by AEE — Dubble Entery”
confirmed [1]
Remarks written by officials in the IFMS approval chain
21 Sep 2021cumulative payments29 Mar 2023
5 · Completion
Status
Completed (final bill)
inferred [1]
Inferred from the final bill: BBMP raises the final bill when measurement of the completed work is recorded
Work started
Unknown
unknown
Actual start date is not published
Expected completion
Unknown
unknown
Stipulated period of completion not found in any public record
Final bill
Completed on
Unknown
unknown
Final bill does not carry an end date
Completion certificate date
24 Sep 2020
inferred [1]
Completion date stated in the Completion Certificate (read by OCR from the scanned document)
6 · Physical evidence
Site photos
Quantities: Schedule B vs billed — read from scanned documents; only rows where quantity × rate = amount are used
| Item | Unit | Planned | Rate | Billed / measured | Difference | Basis | Confidence | Source |
|---|---|---|---|---|---|---|---|---|
| s per . MORTH specification clause No. complete in all respects Cum Rupees: Right Thousand | cum | 2,624.94 | ₹8,000 | — | — | not billed / not read | high | [1] |
| d R oO Th d compacting with plate vibrator having tons compaction force thereby Sqm Se asa | sqm | 10,711.80 | ₹1,200 | — | — | not billed / not read | high | [1] |
| g and finishing cutting including formwork, curing, including Nos Sixty Six and Eleven .63 | nos | 18,833.00 | ₹366 | 16,362.00 | -13% | bill form total up to date | medium | [1] [2] |
| dred masonry as per specifications . & as directed by the Engineer In Sqm up ees me Sunere | sqm | 5,659.61 | ₹950 | 2,094.95 | -63% | bill abstracts (sum of read bills) | high | [1] [2] |
| icely finished jincluding providing holes in the cover slabs wherever necessary for Sqm ee | sqm | 2,795.70 | ₹1,800 | — | — | not billed / not read | high | [1] |
| rriage of mixed method of tipper to site, laying in uniform layers Cum Rupees Two Thousand | cum | 2,101.51 | ₹2,000 | — | — | not billed / not read | high | [1] |
| machine mixed, machine mixed, concrete laid in layers not exceeding Cum HAUpeRS a Thousand | cum | 886.34 | ₹4,000 | — | — | not billed / not read | high | [1] |
| F machine mixed, concrete laid in layers not exceeding cms. thick, cum ees Hive Thonsanil | cum | 417.06 | ₹5,500 | 336.74 | -19% | bill abstracts (sum of read bills) | medium | [1] [2] |
| nd stock piling at designated locations and disposal of dismantled Cum Rupees Nine Hundred | cum | 2,147.92 | ₹995 | — | — | not billed / not read | high | [1] |
| ize of cms thick and fixed in cement mortar ( : ) including fixing Sam Rupees One Thousand | — | 1,365.66 | ₹1,000 | — | — | not billed / not read | medium | [1] |
| R Two Th d Carriage of mixed materialto work site, spreading in uniform layers Cum aS nee | cum | 387.60 | ₹2,000 | — | — | not billed / not read | high | [1] |
| ot less than cms high, bond stones at two m. apart in each course Cum Rupees Five Thousand | cum | 142.70 | ₹5,000 | — | — | not billed / not read | high | [1] |
| ading, grading to required slope and compacting to meet requirement Table Cum Rup eet teen | cum | 1,949.97 | ₹360 | 370.12 | -81% | bill abstracts (sum of read bills) | high | [1] [2] |
| is finished wath fash pointing Rupees OneThonsand ). ‘ ; . : , ‘ . Sqm Three Hundred Fifty | sqm | 445.00 | ₹1,350 | — | — | not billed / not read | high | [1] |
| Seventeen RCC rings and placing 150mm thick precast cover slabs as per Nos Thousand Seven | nos | 32.00 | ₹17,750 | — | — | not billed / not read | high | [1] |
| as per specification & as directed by the Engineer In Charge of the m Rupees One. Eng rem | m | 4,414.08 | ₹116 | 286.92 | -94% | bill abstracts (sum of read bills) | high | [1] [2] |
| ecifications. (only chamfered length shall be recorded) complete as Rmtr Rupees Sixty Only | — | 7,587.00 | ₹60 | — | — | not billed / not read | medium | [1] |
| rage compressive strength N/mm2 confirming to IS (Part) : and constructed with CM Sqm a ia | sqm | 371.84 | ₹1,050 | — | — | not billed / not read | high | [1] |
| th . : superplasticisers @ 3ltrs otros to IS - concrete laid in Cum Rup Ges Hive ‘Pipusand | cum | 57.78 | ₹5,500 | 24.62 | -57% | bill form total up to date | medium | [1] [2] |
| receive bituminous treatment including cost of all materials, labour, Sqm Rupees Five Only | sqm | 63,425.25 | ₹5 | — | — | not billed / not read | high | [1] |
| g o jroad surface and spraying primer at the rate of kg / sqm using Sqm Rupees Thirty Only | sqm | 5,359.15 | ₹30 | 1,339.79 | -75% | bill abstracts (sum of read bills) | medium | [1] [2] |
| f size 450x200x400 mm made out of CC : : and finished with cM L33 Cum! Rupees Five Hundred | cum | 248.00 | ₹500 | — | — | not billed / not read | high | [1] |
| e slopes, in accordance with requirements of lines, grades and cross Cum Rupees Fifty Only | cum | 1,487.21 | ₹50 | 934.04 | -37% | bill abstracts (sum of read bills) | high | [1] [2] |
| kness, including attached pilasters, buttresses, plinth cills and Sqm Rupees EMERS Hundred | sqm | 205.44 | ₹350 | — | — | not billed / not read | high | [1] |
| n etc. including cost of screens and welding rods or bolts and nuts Cum Reapers = Thousand | cum | 1.82 | ₹8,000 | — | — | not billed / not read | high | [1] |
Running-bill figures show progress at that bill, not final quantities. Comparisons are inferred; see methodology.
Timeline
- 21 Sep 2021 First and Final bill ₹4.90 L paid source
- 27 Apr 2022 Running bill ₹1.69 Cr paid source
- 27 Apr 2022 Running bill ₹92.37 L paid source
- 27 Apr 2022 Running bill ₹1.16 Cr paid source
- 27 Apr 2022 Running bill ₹4.04 Cr paid source
- 23 Jan 2023 Fifth and Final bill ₹2.15 Cr paid source
- 29 Mar 2023 First and Final bill ₹4.96 L paid source
Bills & payments (BBMP)
| Bill type | Bill reg. (BR) | Work order | Gross | Nett | Payment | Payee | Source |
|---|---|---|---|---|---|---|---|
| First and Final | 000105 · 13 Aug 2021 | — | ₹4,89,700 | ₹4,40,730 | RTGS 000203 21 Sep 2021 | H & P CONSULTANTS | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
| Running | 000203 · 13 Jan 2022 | — | ₹1,68,81,774 | ₹1,60,56,974 | RTGS 000049 27 Apr 2022 | V M R CONSTRUCTION | BBMP Work Orders 2022-23 · row 5854 |
| Running | 000204 · 13 Jan 2022 | — | ₹92,37,498 | ₹87,86,179 | RTGS 000049 27 Apr 2022 | V M R CONSTRUCTION | BBMP Work Orders 2022-23 · row 5855 |
| Running | 000202 · 13 Jan 2022 | — | ₹1,15,78,480 | ₹1,10,12,759 | RTGS 000049 27 Apr 2022 | V M R CONSTRUCTION | BBMP Work Orders 2022-23 · row 5857 |
| Running | 000211 · 19 Jan 2022 | — | ₹4,04,27,114 | ₹3,83,30,828 | RTGS 000049 27 Apr 2022 | V M R CONSTRUCTION | BBMP Work Orders 2022-23 · row 5856 |
| Fifth and Final | 000042 · 18 May 2022 | — | ₹2,14,53,169 | ₹2,02,52,745 | RTGS 001084 23 Jan 2023 | V M R CONSTRUCTION | BBMP Work Orders 2022-23 · row 5885 |
| First and Final | 000135 · 12 Dec 2022 | — | ₹4,95,600 | ₹4,46,040 | RTGS 001452 29 Mar 2023 | INFRA TECHNOCRATS CO | BBMP Work Orders 2022-23 · row 5891 |
Original system: BBMP Works Bill Public View / IFMS (account.bbmpgov.in). Linked files are public exports of that data on OpenCity.
Why this is a Koramangala project
Work description names Koramangala: "…footpath and other development works in Koramangala K R Garden Koramangala Villag…"