Roads · job 151-20-000081
Improvement works at H T Line SWM Unit and providing cobble pavers other works in 5th Block Koramangala in ward no 151
₹49.52 Lcontract / award · inferred
₹55.47 Lpaid, gross
1bills
13 May 2022last activity
- Planned
- Contracted
- Work documented
- Paid
- Completed
- Physical evidence
no tender found for these bills
Signals — patterns worth a closer look, not findings of wrongdoing
-
info Contractor holds 2% of Koramangala money (8 projects) inferred
C0017 AWIKA CONSTRUCTIONS (identity inferred; ids: KPPP:17612): ₹138,251,234 across 8 projects in this dataset. Concentration is common for ward maintenance contracts; it is context, not a finding.
Related: bscc-2025-26-ow-work-indent20, 151-20-000102, 148-20-000026, 151-20-000079, 151-18-000023, 151-17-000035 …
1 · What was planned
Work
Improvement works at H T Line SWM Unit and providing cobble pavers other works in 5th Block Koramangala in ward no 151
confirmed [1]
Where
5th Block Koramangala
inferred
Place names read from the work description text
Ward
Estimated cost
Unknown
unknown
No estimate published for this work in the sources used
Tender published
Unknown
unknown
No tender found or matched for this work
Time allowed
Unknown
unknown
No tender document found or matched
2 · Who got the work (contract)
Contractor
Contractor identity
C0017 · AWIKA CONSTRUCTIONS
inferred [1]
Resolved contractor C0017 “AWIKA CONSTRUCTIONS”; identifiers: KPPP:17612; name variants joined by: same / truncated name ×1, KPPP name matches IFMS payee name ×2. Also appears as: HITESH KUMAR S( Awika Constructions ), Hitesh kumar S, Sri. Hitesh Kumar S.
Contract value
₹49.52 L
inferred [1]
Contract / tender price stated in the Work Order (read by OCR from the scanned document)
3 · Work documented
Bills recorded
0 running, 1 final paid/registered
confirmed [1]
Bill types recorded in BBMP IFMS for this job's work bills
4 · Money paid
Paid (gross)
Paid (nett)
Paid vs contract
Bills
First payment
Last payment
Bill → payment (median days)
Approval remarks
9 remark(s); e.g. 2022-05-12: “Approved by AdCF — Approved”
confirmed [1]
Remarks written by officials in the IFMS approval chain
5 · Completion
Status
Completed (final bill)
inferred [1]
Inferred from the final bill: BBMP raises the final bill when measurement of the completed work is recorded
Work started
Unknown
unknown
Actual start date is not published
Expected completion
Unknown
unknown
Stipulated period of completion not found in any public record
Final bill
Completed on
Unknown
unknown
Final bill does not carry an end date
6 · Physical evidence
Timeline
- 13 May 2022 First and Final bill ₹55.47 L paid source
How the tender and the bills were connected
Tenders and BBMP bills share no common number, so connections are inferred from independent evidence. Accepted links feed the facts above (marked inferred); possible ones are listed only for review and change nothing.
Possible — not merged ·
amrut_btm.pdf#26 (BBMP tender list 2013–18) ·
confidence possible · description similarity 48%
“Construction of Cobble stone paver, Asphalt to roads in Koramangala , Village in ward No.151 Koramangala” source
✓ same kind of work (road) · ward numbers agree · bills start 225 days after tender · paid is 56% of tender value
✗ different places named (koramangala village vs block5)
Possible — not merged ·
amrut_btm.pdf#28 (BBMP tender list 2013–18) ·
confidence possible · description similarity 53%
“Asphalting to Roads and Improvements to Foot paths in 3rd Block \ , and surrounding area in Koramangala ward No.151” source
✓ same kind of work (road) · ward numbers agree · bills start 225 days after tender
✗ different places named (block3 vs block5)
Possible — not merged ·
amrut_btm.pdf#68 (BBMP tender list 2013–18) ·
confidence possible · description similarity 50%
“Balance developments works at triangle park, rectangular Park at 4th x, block Koramangala and surrounding area of BTM Layout Assembly C Constituency in ward No.151” source
✓ ward numbers agree · bills start 225 days after tender · paid is 62% of tender value
✗ different kind of work (park vs road)
Bills & payments (BBMP)
| Bill type | Bill reg. (BR) | Work order | Gross | Nett | Payment | Payee | Source |
|---|---|---|---|---|---|---|---|
| First and Final | 000266 · 28 Mar 2022 | — | ₹55,46,635 | ₹51,35,428 | RTGS 000101 13 May 2022 | AWIKA CONSTRUCTIONS | BBMP Work Orders 2022-23 · row 5796 |
Original system: BBMP Works Bill Public View / IFMS (account.bbmpgov.in). Linked files are public exports of that data on OpenCity.
Why this is a Koramangala project
Booked to Koramangala ward (151 under the 198-ward map)