Roads, drains & footpaths (combined) · job 151-18-000012

Construction of RCC Box Culvert and drains at 80 feet Ring Road opposite to BMTC and Construction of drain at Jakkasandra extension in ward No.151

Completed (final bill) Bruhat Bengaluru Mahanagara Palike
—contract / award · unknown
₹1.52 Crpaid, gross
2bills
12 Oct 2018last activity
  1. Planned
  2. Contracted
  3. Work documented
  4. Paid
  5. Completed
  6. Physical evidence
no tender found for these bills

This project was reviewed for the investigation cases and set aside: why.

1 · What was planned

Work
Construction of RCC Box Culvert and drains at 80 feet Ring Road opposite to BMTC and Construction of drain at Jakkasandra extension in ward No.151 confirmed [1]
Where
80 Feet Ring Road; Jakkasandra Extension inferred
Place names read from the work description text
Ward
151 (198-ward map) confirmed [1]
Ward the bills are booked to
Estimated cost
Unknown unknown
No estimate published for this work in the sources used
Tender published
Unknown unknown
No tender found or matched for this work
Time allowed
Unknown unknown
No tender document found or matched

2 · Who got the work (contract)

Contractor
Manjunath S confirmed [1]
Payee with the largest billed amount under this job number
Contractor identity
C0119 · Manjunath S confirmed [1]
Resolved contractor C0119 “Manjunath S”; identifiers: no official identifier in the data; name variants joined by: single name variant.
Contract value
Unknown unknown
Contract (work-order) value is not published in BBMP bill data and no awarded tender was matched

3 · Work documented

Bills recorded
1 running, 1 final paid/registered confirmed [1] [2]
Bill types recorded in BBMP IFMS for this job's work bills
Work documents
Completion Certificate ×1; Inspection Report ×2; M.B ×4; Quality Certificate ×2; Road History ×2 confirmed [1] [2] +2
Documents attached to the bills in IFMS (their presence is recorded; contents are not verified)
Quantities: planned vs billed
4 of 8 planned items compared (Schedule B (contract BOQ) vs bill abstracts); median quantity difference +0% inferred [1] [2] +4
Planned quantities (Schedule B / estimate) against billed (bill abstracts) and measured (typed MB sheets) quantities. Only rows where quantity × rate = amount on the scanned page are used; handwritten MB pages are left unread. Never overrides IFMS amounts.
↳ from a tender matched to these bills (none confidence) — why

4 · Money paid

Paid (gross)
₹1.52 Cr confirmed [1]
Sum of 2 bill(s) under the job number
Paid (nett)
₹1.46 Cr confirmed [1]
Gross minus statutory deductions (tax, security deposit, etc.)
Bills
2 confirmed [1]
Unique bills after merging duplicates across exports
First payment
12 Oct 2018 confirmed [1]
Earliest payment (CBR/RTGS) date
Last payment
12 Oct 2018 confirmed [1]
Latest payment (CBR/RTGS) date
Bill → payment (median days)
304 confirmed [1]
Median days from bill registration to RTGS payment over 2 IFMS bill(s)
Approval remarks
27 remark(s); e.g. 2018-10-11: “Approved by CAO — Approved for payment as per the verification report” confirmed [1]
Remarks written by officials in the IFMS approval chain
12 Oct 2018cumulative payments12 Oct 2018

5 · Completion

Status
Completed (final bill) inferred [1]
Inferred from the final bill: BBMP raises the final bill when measurement of the completed work is recorded
Work started
Unknown unknown
Actual start date is not published
Expected completion
Unknown unknown
Stipulated period of completion not found in any public record
Final bill
Raised 17 Jan 2018 confirmed [1]
A bill of type “Second and Final” exists
Completed on
Unknown unknown
Final bill does not carry an end date

6 · Physical evidence

Site photos
6 site photo(s) attached (before / during / after as labelled); no GPS on any photo checked confirmed [1] [2] +2
Photos attached to the bills in IFMS (type as labelled by the uploader)

Quantities: Schedule B vs billed — read from scanned documents; only rows where quantity × rate = amount are used

ItemUnitPlannedRateBilled / measuredDifferenceBasisConfidenceSource
size graded granite metal coarse aggregates @ .7cum and fine aggregates @047cum Cum ae oacum 234.00 ₹6,600 — — not billed / not read high [1]
materials by tipper to site, laying in uniform layers with paver in Cum Eight Han red Onlycum 744.39 ₹1,800 744.39 +0% bill form total up to date high [1] [2]
members wherever necessary complete as per design (laps, hooks and) MT Rupees Sixty Seven— 14.89 ₹67,000 — — not billed / not read medium [1]
nd » aggregate gradation after blending to be as per TAble - cement content no! Cum pee: ,cum 248.13 ₹3,700 248.13 +0% bill form total up to date high [1] [2]
and bed (average thickness) and compacting with plate Rupees Eight Hundred 1s, : . : Sqm =sqm 387.45 ₹870 — — not billed / not read medium [1]
tation, loading, unloading etc, complete as per the directions of the Cum Two Hundred Onlycum 64.00 ₹5,200 121.00 +89% bill abstracts (sum of read bills) medium [1] [2]
e ends, _ Rupees One Whousand /and fixing collars with cement mortar : includi ‘ od M peesm 21.00 ₹1,200 — — not billed / not read high [1]
new plastered i J concrete surfaces complete as per specifications. Sqm Rupees Fourty Onlysqm 153.90 ₹40 105.30 -32% bill abstracts (sum of read bills) high [1] [2]

Running-bill figures show progress at that bill, not final quantities. Comparisons are inferred; see methodology.

Timeline

  1. 12 Oct 2018 Running bill ₹79.09 L paid source
  2. 12 Oct 2018 Second and Final bill ₹73.28 L paid source

Bills & payments (BBMP)

Bill typeBill reg. (BR)Work orderGrossNettPaymentPayeeSource
Running 000063 · 12 Dec 2017 — ₹79,09,000₹74,20,400 RTGS 000228 12 Oct 2018 Manjunath S BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None
Second and Final 000106 · 17 Jan 2018 — ₹73,28,500₹71,31,000 RTGS 000228 12 Oct 2018 Manjunath S BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None

Original system: BBMP Works Bill Public View / IFMS (account.bbmpgov.in). Linked files are public exports of that data on OpenCity.

Why this is a Koramangala project

Booked to Koramangala ward (151 under the 198-ward map) (ward map inferred from the job-code year)