Case file · KP6-151-23-000003
set asideExecuted quantities identical to Schedule B
This project was reviewed and set aside: every issue was explained, was an artefact, or rests only on low-confidence evidence
Project
Comprehensive Development and Asphalting to roads and Construction of RCC Drains, Culvert, Cobble stone pavers and Footpath improvements and other Development works at 7th Block Koramangala (Balance roads), 10th to 17th cross roads and surrounding area in Muniswamy Gowda road, Ashwini layout, Yellamma Temple, VGS Temple, Stanley House roads in Ejipura, 5th and 3rd Block in Koramangala, HSR Layout 6th sector, behind Metro Station and Electrical Srinivasa House roads in Jakkasandra in ward No.147, 148, 151 and 173 (Package No. 03)
Job 151-23-000003 · Roads, drains & footpaths (combined) · 7th Block Koramangala; 17th Cross Road; Ejipura; 3rd Block; Jakkasandra · Bruhat Bengaluru Mahanagara Palike
Contractor: LOKESH R · paid to, per IFMS bills: LOKESH R ₹10.00 Cr (2022-12-31 → 2023-10-31); ROAD INVENTO CONSULT ₹4.93 L (2023-02-23 → 2023-02-23); TECHNOART CONSULTANT ₹8.75 L (2023-07-11 → 2024-01-25)
What was promised
- Contract / work-order value
- ₹8.94 Cr (inferred)
- Estimate
- —
- Work order
- —
- Stipulated completion
- —
What happened
- Paid (gross / net)
- ₹10.13 Cr / ₹9.18 Cr
- Bills
- 5 · 30 Mar 2023 → 23 Aug 2024
- Final bill
- 25 Jan 2024
- Status
- Completed (final bill)
Why this case deserves follow-up
Examined and set aside on this project:
- quantities identical to plan (artefact): the 'identical' quantities came from a running bill's up-to-date column; the comparative statement records different final executed quantities (1,205.16 tendered → 1,771.56 executed; 135.36 tendered → 433.21 executed), leaving fewer than three identical items.
Possible legitimate explanations
- Quantities fixed by drawings (e.g. counted items, standard sections) are executed exactly as designed.
- The item was measured once and the measurement equalled the estimate.
- The estimate itself was prepared from detailed measurements of the site.
What would resolve it
- MB pages with the actual dimensions for these items
- Site measurement of the items
Questions an investigator could ask
- Which MB pages record the measurements of the 1 items on job 151-23-000003 whose executed quantity equals the tendered quantity exactly?
- Who recorded and who check-measured these items, and on what dates?
- Were these items measured on site or carried over from the estimate?
Specific records to request (RTI)
- Measurement-book pages for the items listed — job 151-23-000003; 216 cum @ ₹2,767.00; 1,205.16 cum @ ₹12,700.00; 135.36 @ ₹7,550.00. Why: Shows whether the quantities were measured on site or copied from the estimate.
Evidence
IFMS work bills for this job: 562225, 566057, 590360, 610874, 634429
Investigation lead, not an accusation. Every statement on this page is generated from the published case data (JSON).