Water supply & sewerage
Tender for the work of replacement of 100mm dia CI line by 100mm dia DI water supply pipe line to reduce UFW and to improve water supply facilities to 4th block, Koramangala-2 coming under Koramangala service station of AEESE-5 sub division
₹3.27 Crcontract / award · confirmed
—paid, gross
0bills
28 Oct 2025last activity
- Planned
- Contracted
- Work documented
- Paid
- Completed
- Physical evidence
Tender BWSSB/2024-25/WS/WORK_INDENT1680/CALL-3
tender record only, no bills found yet
Signals — patterns worth a closer look, not findings of wrongdoing
-
notice Tender called 3 times confirmed
Re-calls usually mean no or too few valid bids on earlier calls, which can delay the work and reduce competition. [source]
-
info Two bidders with overlapping names on BWSSB/2024-25/WS/WORK_INDENT1680/CALL-3 confirmed
“VENKATAPPA( SRI VENKATESHWARA ENGINEERING WORK )” (L1) and “VENKATAPPA VENKATESHAIAH (1)( MATHRU SHREE ENGINEERING WORKS )” (L2) both bid. Shared names are common and do not mean the bidders are related. [source]
-
info Near-identical work under another number (BWSSB/2024-25/WS/WORK_INDENT1678/CALL-3) inferred
Descriptions are 89% similar. Could be a recurring annual work, a re-tender, a split of one work, or a duplicate entry.
Related: bwssb-2024-25-ws-work-indent1678 -
info Near-identical work under another number (BWSSB/2024-25/WS/WORK_INDENT1682/CALL-2) inferred
Descriptions are 88% similar. Could be a recurring annual work, a re-tender, a split of one work, or a duplicate entry.
Related: bwssb-2024-25-ws-work-indent1682
1 · What was planned
Work
Tender for the work of replacement of 100mm dia CI line by 100mm dia DI water supply pipe line to reduce UFW and to improve water supply facilities to 4th block, Koramangala-2 coming under Koramangala service station of AEESE-5 sub division
confirmed [1]
Where
4th Block, Koramangala
inferred
Place names read from the work description text
Estimated cost
Budget provision
Tender published
Tender calls
Time allowed
180 days (~6 months)
confirmed [1]
Stipulated period of completion in the tender document (“6 months”, Bid_Document_INDENT_1680 Call-3.docx)
2 · Who got the work (contract)
Contractor
VENKATAPPA( SRI VENKATESHWARA ENGINEERING WORK )
confirmed [1]
Awarded (selected) bidder on the tender
Contractor identity
C0019 · VENKATAPPA( SRI VENKATESHWARA ENGINEERING WORK )
inferred [1]
Resolved contractor C0019 “VENKATAPPA( SRI VENKATESHWARA ENGINEERING WORK )”; identifiers: KPPP:1864; name variants joined by: KPPP name matches IFMS payee name ×1. Also appears as: SRI VENKATESHWARA EN.
Contract value
Bidders
2
confirmed [1]
Bidders in the commercial comparative statement: L1 VENKATAPPA( SRI VENKATESHWARA ENGINEERING WORK ) ₹32,659,107; L2 VENKATAPPA VENKATESHAIAH (1)( MATHRU SHREE ENGINEERING WORKS ) ₹33,366,159
Awarded on
2 bids on BWSSB/2024-25/WS/WORK_INDENT1680/CALL-3
| L1 | VENKATAPPA( SRI VENKATESHWARA ENGINEERING WORK ) | ₹3,26,59,107 |
| L2 | VENKATAPPA VENKATESHAIAH (1)( MATHRU SHREE ENGINEERING WORKS ) | ₹3,33,66,159 |
3 · Work documented
4 · Money paid
Paid (gross)
Unknown
unknown
No bill or payment for this work found in published BBMP data
5 · Completion
Status
Work started
Unknown
unknown
Actual start date is not published
Expected completion
Completed on
Unknown
unknown
No bills yet
6 · Physical evidence
Timeline
Tender notices
| Tender no. | Source | Published | Status | Estimate | Awarded | To | Time allowed | Link | Evidence |
|---|---|---|---|---|---|---|---|---|---|
| BWSSB/2024-25/WS/WORK_INDENT1680/CALL-3 | KPPP | 30 Dec 2024 | Awarded | ₹3.20 Cr | ₹3.27 Cr | VENKATAPPA( SRI VENKATESHWARA ENGINEERING WORK ) | 180 days | exact | record · award · tender doc |
Why this is a Koramangala project
Tender title names Koramangala: "…e water supply facilities to 4th block, Koramangala-2 coming under Koramangala se…"