Drains & storm-water · job 307-19-000009
Construction of parallel Drain to SWD K-100 by laying RCC hume Pipes all along the Koramangala 80 feet Road from Sony World Junction via Maharaja Signal to Belanduru lake and othe area alternate drains for carrying the excess water of Koramangala and adjacent areas to Bellandur lake
—contract / award · unknown
₹24.11 Crpaid, gross
11bills
14 Sep 2021last activity
- Planned
- Contracted
- Work documented
- Paid
- Completed
- Physical evidence
Tender BBMP/2017-18/FP/WORK_INDENT28554
tender ↔ bills linked by matching (high confidence)
This project was reviewed for the investigation cases and set aside: why.
Signals — patterns worth a closer look, not findings of wrongdoing
- notice Blank / placeholder file used as a site photo confirmed
-
notice 10 bill(s) registered after the final bill confirmed
Final bill registered 2019-03-08; later non-final bills exist. [source]
-
notice Billed quantity above plan (2 items) inferred
iron section, m in height, horizontal rail painted ( coats) with yellow and Each — planned 100 nos (Schedule B), bill abstracts (sum of read bills) 150 (+50%); gregates @ .459cum machine mixed, concrete laid in layers not exceeding cms. cum — planned 738.05 cum (Schedule B), bill abstracts (sum of read bills) 967.85 (+31%). Possible explanations: approved deviation or supplementary schedule, site conditions, an OCR misread on the plan side (each row passed quantity × rate = amount). [source] [source]
1 · What was planned
Work
Construction of parallel Drain to SWD K-100 by laying RCC hume Pipes all along the Koramangala 80 feet Road from Sony World Junction via Maharaja Signal to Belanduru lake and othe area alternate drains for carrying the excess water of Koramangala and adjacent areas to Bellandur lake
confirmed [1]
Where
80 Feet Road; Maharaja Signal; 80Feet Road
inferred
Place names read from the work description text
Estimated cost
Unknown
unknown
No estimate published for this work in the sources used
Tender published
Tender calls
Time allowed
Unknown
unknown
Tender document not available or period not stated
2 · Who got the work (contract)
Contractor
H D INFRASTRUCTURES
confirmed [1]
Payee with the largest billed amount under this job number; also billed: Civil Quality Consultants and Engineers Pro Smt. Mamatha K N, M/s Civil Tech Labs Pro Sri Basavaraj K, M/s. Sapience Consultants and Engineers
Contractor identity
C0029 · H D INFRASTRUCTURES
confirmed [1]
Resolved contractor C0029 “H D INFRASTRUCTURES”; identifiers: no official identifier in the data; name variants joined by: single name variant.
Contract value
Unknown
unknown
Contract (work-order) value is not published in BBMP bill data and no awarded tender was matched
3 · Work documented
Bills recorded
Work documents
Quantities: planned vs billed
16 of 45 planned items compared (Schedule B (contract BOQ) vs bill abstracts); median quantity difference -9%
inferred [1] [2] +4
Planned quantities (Schedule B / estimate) against billed (bill abstracts) and measured (typed MB sheets) quantities. Only rows where quantity × rate = amount on the scanned page are used; handwritten MB pages are left unread. Never overrides IFMS amounts.
↳ from a tender matched to these bills (high confidence) — why
4 · Money paid
Paid (gross)
Paid (nett)
Bills
First payment
Last payment
Unpaid / pending bills
1 bill(s) not paid (₹0); at: ? ×1
confirmed [1]
Bills present in IFMS without an RTGS payment (drafts or bills awaiting approval); not counted as paid
Bill → payment (median days)
Approval remarks
118 remark(s); e.g. 2021-05-29: “Forwarded — Verified the work bill as per the Chief Commissioner Approval E Office No.7753 202-22 Note 108 Dated 25-05-2021 and Special Commissioner Finance app”
confirmed [1]
Remarks written by officials in the IFMS approval chain
24 Apr 2019cumulative payments14 Sep 2021
5 · Completion
Status
Completed (final bill)
inferred [1]
Inferred from the final bill: BBMP raises the final bill when measurement of the completed work is recorded
Work started
Unknown
unknown
Actual start date is not published
Expected completion
Unknown
unknown
Stipulated period of completion not found in any public record
Final bill
Completed on
Unknown
unknown
Final bill does not carry an end date
Extensions of time
6 · Physical evidence
Site photos
Quantities: Schedule B vs billed — read from scanned documents; only rows where quantity × rate = amount are used
| Item | Unit | Planned | Rate | Billed / measured | Difference | Basis | Confidence | Source |
|---|---|---|---|---|---|---|---|---|
| joints with jack to correct position including cost of jointing materials ie., rubber Rmt | m | 2,246.00 | ₹22,500 | — | — | not billed / not read | high | [1] |
| toration of site after completion s per approved specifications, rules and regulations RMT | m | 300.00 | ₹1,61,000 | 95.00 | -68% | bill form total up to date | high | [1] [2] |
| gregates @ .47cum, with superplastisiser @3lts confirming to IS9103- Reaffirmed- ,Open cum | cum | 1,764.41 | ₹8,000 | 1,914.74 | +8% | bill abstracts (sum of read bills) | medium | [1] [2] |
| trap broken Wl metal 100mm. and down size, with approved sand including hand packing, cum | cum | 4,155.31 | ₹2,500 | — | — | not billed / not read | high | [1] |
| t pipes Pipe reinforced of NP3 Class forming to IS with latest for 300mm dia (BWSSB SR Rmt | m | 3,696.00 | ₹1,922 | — | — | not billed / not read | high | [1] |
| 250mm_ layers ‘ wherever necessary watering and ramming, including cost of materials, Cum | cum | 1,320.00 | ₹3,500 | — | — | not billed / not read | high | [1] |
| ls at any thickness, including attached pilasters, buttresses, plinth cills and string sqm | sqm | 10,738.00 | ₹350 | 9,367.79 | -13% | bill abstracts (sum of read bills) | medium | [1] [2] |
| nd fine aggregates @ .459cum machine mixed, concrete laid in layers not exceeding cms. cum | cum | 738.05 | ₹4,500 | 967.85 | +31% | bill abstracts (sum of read bills) | high | [1] [2] |
| h paver / finisher to the required level and grade, rolling by power roller to achieve cum | cum | 534.00 | ₹5,800 | — | — | not billed / not read | high | [1] |
| rolling with - . wheeled steel/vibratory roller - tonnes in stages to proper grade and cum | cum | 1,335.00 | ₹1,900 | — | — | not billed / not read | high | [1] |
| , rolling with - Py wheeled steel/vibratory roller - tonnes: in stages to proper grade and | tonne | 1,335.00 | ₹1,697 | — | — | not billed / not read | high | [1] |
| ace such as suspended floors, roofs, landings, balconies and likes, thickness above mm sqm | sqm | 4,700.00 | ₹450 | — | — | not billed / not read | high | [1] |
| er in- charge.PWD SR - Heavy Duty Grating with mm Dia MS bars with equal spacing of mm Sqm | sqm | 940.28 | ₹2,200 | — | — | not billed / not read | high | [1] |
| smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per cum | cum | 267.00 | ₹7,500 | — | — | not billed / not read | high | [1] |
| on of shoring and bracing, removal of stumps and other deleterious matter, dressing of cum | cum | 6,588.00 | ₹300 | 7,492.24 | +14% | bill abstracts (sum of read bills) | medium | [1] [2] |
| stumps and other deleterious matter, dressing of sides and bottom and backfilling with cum | cum | 7,098.21 | ₹250 | 30,156.75 | +325% | bill abstracts (sum of read bills) | medium | [1] [2] |
| pper at loading point, loading with front end loader,dumping, turning for return trip, cum | cum | 22,399.77 | ₹75 | 5,599.94 | -75% | bill abstracts (sum of read bills) | high | [1] [2] |
| ing and ; bracing, removal of StumTips and other deleterious matter, dressing of sides cum | cum | 6,588.00 | ₹250 | — | — | not billed / not read | high | [1] |
| he material with water at OMC in mechanical mix plant carriage of mixed method of tipper . | — | 801.00 | ₹1,940 | — | — | not billed / not read | medium | [1] |
| ing each deposited layer . by ramming after watering with lead upto 50m.and_ lift upto Cum | cum | 14,828.00 | ₹100 | — | — | not billed / not read | high | [1] |
| material with water at OMC in mechanical mix plant carriage of mixed method of tipper cum | cum | 801.00 | ₹1,800 | 955.56 | +19% | bill abstracts (sum of read bills) | high | [1] [2] |
| rting to site, spreading, grading to required slope and compacting to meet requirement cum | cum | 2,670.00 | ₹400 | 955.18 | -64% | bill abstracts (sum of read bills) | high | [1] [2] |
| porting to site, . spreading, grading to required slope and compacting to meet requirement | — | 2,670.00 | ₹351 | 2,440.41 | -9% | bill abstracts (sum of read bills) | medium | [1] [2] |
| mooth and fixing jof pipes in CC : : with graded metal of 20mm and down size including nos | nos | 30.00 | ₹26,079 | 6.00 | -80% | bill abstracts (sum of read bills) | medium | [1] [2] |
| cification, A.Granular Meterial with all lead and lifts, etc., after breaking of clods Cum | cum | 2,871.60 | ₹250 | — | — | not billed / not read | high | [1] |
| n of shoring Jand bracing, removal of stumps and other deleterious matter, dressing of cum | cum | 2,242.34 | ₹300 | — | — | not billed / not read | high | [1] |
| shoring and bracing, removal of stumps and other deleterious matter, dressing of sides cum | cum | 2,242.34 | ₹250 | 7,969.77 | +255% | bill abstracts (sum of read bills) | medium | [1] [2] |
| this reel insulator of suitable core through which insulated wire passes and this reel Rmt | m | 4,652.00 | ₹100 | — | — | not billed / not read | high | [1] |
| coat with S.S bitumen % emulsion on prepared surface of granular base such as WBM, WMM sqm | sqm | 10,680.00 | ₹38 | 2,628.45 | -75% | bill form total up to date | high | [1] [2] |
| attached with scarifier without disturbing the base and stacking the debris including Sqm | sqm | 13,001.00 | ₹30 | 3,397.97 | -74% | bill abstracts (sum of read bills) | high | [1] [2] |
| imer coat with S.S bitumen emulsion on prepared surface of granular base such as WBM, WMM) | — | 10,680.00 | ₹35 | — | — | not billed / not read | medium | [1] |
| eight .70m with clear height of not less than m from the ground level to the bottom of the | m | 60.00 | ₹6,146 | — | — | not billed / not read | high | [1] |
| mm angle iron section, m in height, horizontal rail painted ( coats) with yellow and Each | nos | 100.00 | ₹3,000 | 150.00 | +50% | bill abstracts (sum of read bills) | high | [1] [2] |
| t .70m with clear height of not less than m from the ground level to the bottom of the nos | nos | 60.00 | ₹5,000 | — | — | not billed / not read | high | [1] |
| f low density polyethylene (LDPE) material with a square base of x x mm anda height of Nos | nos | 300.00 | ₹650 | — | — | not billed / not read | high | [1] |
| even shade after throughly brooming the surface to remove all dirt and loose powdered sqm | sqm | 2,000.00 | ₹90 | — | — | not billed / not read | high | [1] |
| its accessories such as rubber gaskets made of SBR/EPDM on the socket face making the nos | nos | 151.00 | ₹850 | — | — | not billed / not read | high | [1] |
| g T&P and > scaffolding wherever necessary, sorting the dismantled material, disposal cum! | cum | 277.20 | ₹400 | 6.96 | -98% | bill form total up to date | high | [1] [2] |
| ing _ setting out,construction of shoring and bracing, removal of stumps and other . . . . | — | 147.29 | ₹400 | — | — | not billed / not read | medium | [1] |
| giving hydraulic test as per relevant ISS with all lead and lift including testing and Rmt | m | 4,600.00 | ₹12 | — | — | not billed / not read | high | [1] |
Running-bill figures show progress at that bill, not final quantities. Comparisons are inferred; see methodology.
Timeline
- 03 Feb 2018 Tender BBMP/2017-18/FP/WORK_INDENT28554 published inferred source
- 24 Apr 2019 First and Final bill ₹29.99 L paid source
- 21 Jun 2019 Running bill ₹2.60 Cr paid source
- 02 Aug 2019 Running bill ₹1.57 Cr paid source
- 05 Jun 2020 Running bill ₹4.00 Cr paid source
- 24 Dec 2020 Running bill ₹4.22 Cr paid source
- 24 Dec 2020 Running bill ₹4.60 L paid source
- 26 Mar 2021 Running bill ₹4.44 Cr paid source
- 29 May 2021 Running bill ₹9.77 L paid source
- 29 May 2021 Running bill ₹5.29 L paid source
- 12 Jul 2021 Running bill ₹3.88 Cr paid source
- 14 Sep 2021 Running bill ₹2.91 Cr paid source
How the tender and the bills were connected
Tenders and BBMP bills share no common number, so connections are inferred from independent evidence. Accepted links feed the facts above (marked inferred); possible ones are listed only for review and change nothing.
Linked ·
BBMP/2017-18/FP/WORK_INDENT28554 (BBMP tender list 2013–18) ·
confidence high · description similarity 98%
“Construction of Parallel Drain to SWD K-100 by laying RCC Hume pipes all along the Koramangala 80 feet road from Sony world junction via Maharaja Signal to Bellanduru lake and other areas alternate drains for carrying the excess water of Koramangala and adjacent areas to Bellanduru lake.” source
✓ same kind of work (drain, road) · same place(s): 80 feet road, sony world · bills start 398 days after tender
Tender notices
| Tender no. | Source | Published | Status | Estimate | Awarded | To | Time allowed | Link | Evidence |
|---|---|---|---|---|---|---|---|---|---|
| BBMP/2017-18/FP/WORK_INDENT28554 | BBMP list | 03 Feb 2018 | Tender published (outcome not in this list) | — | — | — | — | high | record · row 4864 |
Bills & payments (BBMP)
| Bill type | Bill reg. (BR) | Work order | Gross | Nett | Payment | Payee | Source |
|---|---|---|---|---|---|---|---|
| First and Final | 000247 · 08 Mar 2019 | — | ₹29,99,000 | ₹26,99,100 | RTGS 000026 24 Apr 2019 | Civil Quality Consultants and Engineers Pro Smt. Mamatha K N | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
| Running | 000039 · 27 May 2019 | — | ₹2,59,64,959 | ₹2,45,47,235 | RTGS 000091 21 Jun 2019 | H D INFRASTRUCTURES | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
| Running | 000074 · 15 Jul 2019 | — | ₹1,56,66,027 | ₹1,47,50,630 | RTGS 000139 02 Aug 2019 | H D INFRASTRUCTURES | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
| Running | 000214 · 28 Jan 2020 | — | ₹3,99,83,560 | ₹3,72,65,200 | RTGS 000063 05 Jun 2020 | H D INFRASTRUCTURES | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
| Running | 000034 · 04 Jun 2020 | — | ₹4,21,77,235 | ₹3,95,40,349 | RTGS 000237 24 Dec 2020 | H D INFRASTRUCTURES | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
| Running | 000038 · 10 Jun 2020 | — | ₹4,60,000 | ₹4,14,000 | RTGS 000237 24 Dec 2020 | M/s. Sapience Consultants and Engineers | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
| Running | 000091 · 24 Nov 2020 | — | ₹9,77,000 | ₹8,79,300 | RTGS 000049 29 May 2021 | M/s Civil Tech Labs Pro Sri Basavaraj K | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
| Running | 000103 · 08 Dec 2020 | — | ₹4,44,24,000 | ₹4,21,52,414 | RTGS 000309 26 Mar 2021 | H D INFRASTRUCTURES | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
| Running | 000152 · 02 Mar 2021 | — | ₹3,88,16,000 | ₹3,61,71,356 | RTGS 000104 12 Jul 2021 | H D INFRASTRUCTURES | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
| Running | 000161 · 18 Mar 2021 | — | ₹5,29,400 | ₹4,76,400 | RTGS 000049 29 May 2021 | M/s Civil Tech Labs Pro Sri Basavaraj K | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
| Running | 000042 · 15 Jul 2021 | — | ₹2,90,95,000 | ₹2,73,78,446 | RTGS 000189 14 Sep 2021 | H D INFRASTRUCTURES | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
Original system: BBMP Works Bill Public View / IFMS (account.bbmpgov.in). Linked files are public exports of that data on OpenCity.
Why this is a Koramangala project
Work description names Koramangala: "…by laying RCC hume Pipes all along the Koramangala 80 feet Road from Sony World…"