Junction Improvements in Koramangala Maharaja signal, Wipro signal and Ishwarya signal
—contract / award · unknown
₹97.29 Lpaid, gross
1bills
09 Jan 2020last activity
- Planned
- Contracted
- Work documented
- Paid
- Completed
- Physical evidence
no tender found for these bills
1 · What was planned
Work
Junction Improvements in Koramangala Maharaja signal, Wipro signal and Ishwarya signal
confirmed [1]
Where
Maharaja Signal; Wipro Signal
inferred
Place names read from the work description text
Estimated cost
Unknown
unknown
No estimate published for this work in the sources used
Tender published
Unknown
unknown
No tender found or matched for this work
Time allowed
Unknown
unknown
No tender document found or matched
2 · Who got the work (contract)
Contractor
Contractor identity
C0249 · K.Somappa
confirmed [1]
Resolved contractor C0249 “K.Somappa”; identifiers: no official identifier in the data; name variants joined by: single name variant.
Contract value
Unknown
unknown
Contract (work-order) value is not published in BBMP bill data and no awarded tender was matched
3 · Work documented
Bills recorded
0 running, 1 final paid/registered
confirmed [1]
Bill types recorded in BBMP IFMS for this job's work bills
4 · Money paid
Paid (gross)
Paid (nett)
Bills
First payment
Last payment
Bill → payment (median days)
Approval remarks
17 remark(s); e.g. 2020-01-09: “Approved by CAO — ಟಿ.ವಿ.ಸಿ.ಸಿರವರ ಅನುಮೋದನೆ ಮೇರೆಗೆ ಸದರಿ ಬಿಲ್ಲನ್ನು ಅನುಮೋದಿಸಿದೆ.”
confirmed [1]
Remarks written by officials in the IFMS approval chain
5 · Completion
Status
Completed (final bill)
inferred [1]
Inferred from the final bill: BBMP raises the final bill when measurement of the completed work is recorded
Work started
Unknown
unknown
Actual start date is not published
Expected completion
Unknown
unknown
Stipulated period of completion not found in any public record
Final bill
Completed on
Unknown
unknown
Final bill does not carry an end date
Extensions of time
6 · Physical evidence
Timeline
- 09 Jan 2020 First and Final bill ₹97.29 L paid source
How the tender and the bills were connected
Tenders and BBMP bills share no common number, so connections are inferred from independent evidence. Accepted links feed the facts above (marked inferred); possible ones are listed only for review and change nothing.
Possible — not merged ·
BBMP/2017-18/OW/WORK_INDENT25882 (BBMP tender list 2013–18) ·
confidence possible · description similarity 100%
“Junction Improvements in Koramangala Maharaja signal, Wipro Signal and Ishwarya Signal” source
✓ no corroboration
✗ bills begin 31 months after the tender (re-tender or a different contract?)
Bills & payments (BBMP)
| Bill type | Bill reg. (BR) | Work order | Gross | Nett | Payment | Payee | Source |
|---|---|---|---|---|---|---|---|
| First and Final | 000016 · 09 Dec 2019 | — | ₹97,29,078 | ₹87,59,579 | RTGS 000338 09 Jan 2020 | K.Somappa | BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None |
Original system: BBMP Works Bill Public View / IFMS (account.bbmpgov.in). Linked files are public exports of that data on OpenCity.
Why this is a Koramangala project
Work description names Koramangala: "…Junction Improvements in Koramangala Maharaja signal, Wipro signal…"