Drains & storm-water · job 151-18-000061
Improvments to drains in 7th cross in 6th Block in ward no 151 Koramangala
—contract / award · unknown
₹17.61 Lpaid, gross
1bills
06 Apr 2022last activity
- Planned
- Contracted
- Work documented
- Paid
- Completed
- Physical evidence
no tender found for these bills
Signals — patterns worth a closer look, not findings of wrongdoing
-
info Median 894 days from bill registration to payment confirmed
Long payment delays are common (seniority-based bill clearance) and raise contractors' financing costs. [source]
-
info Bill paid 2 years after work end date confirmed
Long payment lag; common with BBMP bill backlogs (seniority-based payment). [source]
1 · What was planned
Work
Where
7th Cross; 6th Block
inferred
Place names read from the work description text
Ward
Estimated cost
Unknown
unknown
No estimate published for this work in the sources used
Tender published
Unknown
unknown
No tender found or matched for this work
Time allowed
Unknown
unknown
No tender document found or matched
2 · Who got the work (contract)
Contractor
Contractor identity
C0175 · RAGHU RAMACHANDRA C
confirmed [1]
Resolved contractor C0175 “RAGHU RAMACHANDRA C”; identifiers: no official identifier in the data; name variants joined by: single name variant.
Contract value
Unknown
unknown
Contract (work-order) value is not published in BBMP bill data and no awarded tender was matched
Work order date
3 · Work documented
Bills recorded
0 running, 1 final paid/registered
confirmed [1]
Bill types recorded in BBMP IFMS for this job's work bills
4 · Money paid
Paid (gross)
Paid (nett)
Bills
First payment
Last payment
Bill → payment (median days)
Approval remarks
9 remark(s); e.g. 2022-04-05: “Forwarded — Verified with bill form as per CAO Inter Office Memo No CAO/PR/5272/15-16 dated 26-12-2015. Based on the recommendation of concerned divisional EE a”
confirmed [1]
Remarks written by officials in the IFMS approval chain
5 · Completion
Status
Completed (final bill)
inferred [1]
Inferred from the final bill: BBMP raises the final bill when measurement of the completed work is recorded
Work started
Expected completion
Unknown
unknown
Stipulated period of completion not found in any public record
Final bill
Completed on
6 · Physical evidence
Timeline
How the tender and the bills were connected
Tenders and BBMP bills share no common number, so connections are inferred from independent evidence. Accepted links feed the facts above (marked inferred); possible ones are listed only for review and change nothing.
Possible — not merged ·
BBMP/2017-18/OW/WORK_INDENT27425 (BBMP tender list 2013–18) ·
confidence possible · description similarity 47%
“Improvements to drains in New Model Harijana Colony, Koramangala 8th Block in ward No. 147 (Adugodi)” source
✓ same kind of work (drain) · bills start 493 days after tender · paid is 71% of tender value · same engineering division
✗ different places named (adugodi, block8 vs block6, cross7) · ward numbers differ (tender 147, 176)
Possible — not merged ·
amrut_btm.pdf#22 (BBMP tender list 2013–18) ·
confidence possible · description similarity 59%
“Cosntruction of RCC Box drain and other development works to 17th - B, 17th C and 17th E main road in 6th Block Koramangala and Surrounding area in ward No.151” source
✓ same kind of work (drain) · same place(s): block6 · ward numbers agree
✗ bills start 890 days before the tender · job-number year far from tender year
Possible — not merged ·
BBMP/2025-26/OW/WORK_INDENT7614 (KPPP) ·
confidence possible · description similarity 65%
“Desilting and Improvements to Drain in cross and Main roads and other development works in 6th Block Koramangala and Surrounding area in Ward No.174 Koramangala” source
✓ same kind of work (drain) · same place(s): block6 · ward numbers agree · same engineering division
✗ awarded bidder not among payees · bills start 2281 days before the tender · job-number year far from tender year
Bills & payments (BBMP)
| Bill type | Bill reg. (BR) | Work order | Gross | Nett | Payment | Payee | Source |
|---|---|---|---|---|---|---|---|
| First and Final | 000132 · 25 Oct 2019 | 000520 09 Mar 2019 | ₹17,60,944 | ₹16,84,343 | 06 Apr 2022 | RAGHU RAMACHANDRA C | BBMP Work Orders - Koramangala (Ward 151), 2013-2022 · row 65 |
Original system: BBMP Works Bill Public View / IFMS (account.bbmpgov.in). Linked files are public exports of that data on OpenCity.
Why this is a Koramangala project
Booked to Koramangala ward (151 under the 198-ward map)