Bengaluru Public Works Explorer Koramangala

← All works

Parks & playgrounds · job 151-17-000088

Development of park at south zone Koramangala ward No 151 south zone

Completed (final bill) Bruhat Bengaluru Mahanagara Palike
—contract / award · unknown
₹2.32 Crpaid, gross
1bills
11 Apr 2019last activity
  1. Planned
  2. Contracted
  3. Work documented
  4. Paid
  5. Completed
  6. Physical evidence
Tender BBMP/2017-18/OW/WORK_INDENT27988 tender ↔ bills linked by matching (high confidence)

1 · What was planned

Work
Development of park at south zone Koramangala ward No 151 south zone confirmed [1]
Where
Unknown unknown
No place name could be read from the description
Ward
151 (198-ward map) confirmed [1]
Ward the bills are booked to
Estimated cost
Unknown unknown
No estimate published for this work in the sources used
Tender published
28 Dec 2017 inferred [1]
Date the first call of the tender was published
↳ from a tender matched to these bills (high confidence) — why
Tender calls
1 (first call) inferred [1]
Tender awarded/listed on its first call
↳ from a tender matched to these bills (high confidence) — why
Time allowed
Unknown unknown
Tender document not available or period not stated

2 · Who got the work (contract)

Contractor
Billapur Yellappa Perumaiah confirmed [1]
Payee with the largest billed amount under this job number
Contractor identity
C0237 · Billapur Yellappa Perumaiah confirmed [1]
Resolved contractor C0237 “Billapur Yellappa Perumaiah”; identifiers: no official identifier in the data; name variants joined by: single name variant.
Contract value
Unknown unknown
Contract (work-order) value is not published in BBMP bill data and no awarded tender was matched

3 · Work documented

Bills recorded
0 running, 1 final paid/registered confirmed [1]
Bill types recorded in BBMP IFMS for this job's work bills
Work documents
Completion Certificate ×1; Inspection Report ×1; M.B ×6; Quality Certificate ×1; Road History ×1 confirmed [1] [2] +2
Documents attached to the bills in IFMS (their presence is recorded; contents are not verified)
Quantities: planned vs billed
68 planned items read (Estimate); no billed / measured quantity could be read inferred [1] [2] +2
Planned quantities (Schedule B / estimate) against billed (bill abstracts) and measured (typed MB sheets) quantities. Only rows where quantity × rate = amount on the scanned page are used; handwritten MB pages are left unread. Never overrides IFMS amounts.
↳ from a tender matched to these bills (high confidence) — why

4 · Money paid

Paid (gross)
₹2.32 Cr confirmed [1]
Sum of 1 bill(s) under the job number
Paid (nett)
₹2.19 Cr confirmed [1]
Gross minus statutory deductions (tax, security deposit, etc.)
Bills
1 confirmed [1]
Unique bills after merging duplicates across exports
First payment
11 Apr 2019 confirmed [1]
Earliest payment (CBR/RTGS) date
Last payment
11 Apr 2019 confirmed [1]
Latest payment (CBR/RTGS) date
Bill → payment (median days)
23 confirmed [1]
Median days from bill registration to RTGS payment over 1 IFMS bill(s)
Approval remarks
8 remark(s); e.g. 2019-04-11: “Approved by CAO — Approved for payment as per the verification report” confirmed [1]
Remarks written by officials in the IFMS approval chain

5 · Completion

Status
Completed (final bill) inferred [1]
Inferred from the final bill: BBMP raises the final bill when measurement of the completed work is recorded
Work started
Unknown unknown
Actual start date is not published
Expected completion
Unknown unknown
Stipulated period of completion not found in any public record
Final bill
Raised 19 Mar 2019 confirmed [1]
A bill of type “Final” exists
Completed on
Unknown unknown
Final bill does not carry an end date
Extensions of time
1 extension-of-time order(s): to 2019-03-31 inferred [1]
Extension-of-time orders attached to this job's bills in IFMS, read by OCR. A later order supersedes an earlier one; an order may belong to an earlier contract under the same job.
↳ from a tender matched to these bills (high confidence) — why
Extended completion
31 Mar 2019 inferred [1]
Latest completion date granted by an extension-of-time order found in IFMS.
↳ from a tender matched to these bills (high confidence) — why

6 · Physical evidence

Site photos
3 site photo(s) attached (before / during / after as labelled); no GPS on any photo checked confirmed [1] [2] +1
Photos attached to the bills in IFMS (type as labelled by the uploader)

Quantities: Schedule B vs billed — read from scanned documents; only rows where quantity × rate = amount are used

ItemUnitPlannedRateBilled / measuredDifferenceBasisConfidenceSource
rected by the engineer Inchargeof the work , ost of the plant ( Plants per Sq.m) nea : C .sqm 8,400.00 ₹300 — — not billed / not read high [1]
for planting SOK win, er ane ling % of the area with excavated top soil & remaining. sa. a— 8,400.00 ₹255 — — not billed / not read medium [1]
enance of lawns or turfing of slopes (rough grassing) for a period of year including Sqm @— 20,000.00 ₹90 — — not billed / not read medium [1]
r a _ __ = Cum + — ; Cum _ + fot sen 0s foe . Gam -_ Cum P1500 ___ a Cum ' L —— = es Total— 319.33 ₹4,522 — — not billed / not read medium [1]
upply of : « the te ‘rees and planting ' Height, as directed by the engineer Inchargeof ft— 1,000.00 ₹750 — — not billed / not read medium [1]
" , MOUNDFORMATION: = = °* __ i _ j ~~ Providing & forming mound using red earth by cum “cum 2,000.00 ₹363 — — not billed / not read high [1]
y roughly dressed and fixed in cement mortar ( : ) including fixin curing etc., complete .— 672.60 ₹841 — — not billed / not read medium [1]
no ___234336.00 oodlight 110W,As directed by the engineer incharge of th ee aetna work nonos 32.00 ₹17,593 — — not billed / not read high [1]
, grinding and er “complete as per specifications (pwd SR - p.no41 1NO7.3) . __ ee es — —;— 3,924.57 ₹124 — — not billed / not read medium [1]
mixed, ; : we concrete laid in layers not exceeding cms. thick, well compacted, In cum ..cum 83.64 ₹5,450 — — not billed / not read high [1]
ch, The pole ‘ ; shall be erected in cement concrete work ( : : ) including excavation and— 28.00 ₹15,000 — — not billed / not read medium [1]
IP Benches As directed by the engineer a as oe incharge of the work &As per drawings. Eachnos 26.00 ₹14,160 — — not billed / not read high [1]
il : a —Jeost of the specimen plants Se SO Cycas Revoluta ee a es Ja) 90cm Dia, ¢m ht Eachnos 75.00 ₹4,500 — — not billed / not read high [1]
....mm with . 3mm thick, suitable base plate and 4Nos of..... long J bolts along with Eachnos 45.00 ₹6,091 — — not billed / not read high [1]
epth j . ; - , : of ,15m (1x1x0.15m)as directed by the engineer incharge of the work Cum °cum 600.00 ₹439 — — not billed / not read high [1]
us Nuda / mini Tucci ( 90cm - 150cm Beach __ L—7s000000 _ Ficus Ponda ( cm - ht rach - . =— 100.00 ₹2,500 — — not billed / not read medium [1]
g the trench , P.No- to the required ground level and consolidating etc., complete.(As Mtrm 2,275.00 ₹106 — — not billed / not read high [1]
n 4KV along with Over \.No. sages occ short circult/ miswiring protection. Compatible Eachnos 12.00 ₹18,720 — — not billed / not read high [1]
, walls r (any thickness) including attached pilasters, columnsplllars, posts, struts, cumcum 33.36 ₹6,719 — — not billed / not read high [1]
Planting and maintaining of flowering plants and shrubs-A. Planting flowering plants and @— 9,375.00 ₹23 — — not billed / not read medium [1]
nd breaking of : clumps watering etc. to a depth of .45m (1x1x0,45m).as directed by the. "— 4,000.00 ₹49 — — not billed / not read medium [1]
ame materials in ai : ; p.No- . lexisting trench as per IS part -II suitable for drawing :nos 1,940.00 ₹98 — — not billed / not read high [1]
n dia @150mm</e Ky om - iseof Jammm dia dist @150mm ye kg - anz0o > + pf Tg pp Total (ron)— 2.69 ₹60,534 — — not billed / not read medium [1]
ost towards dibbling/laying of lawn , inclusive of mixing of ingradients, application of .— 4,000.00 ₹41 — — not billed / not read medium [1]
E 6S i)Pulmeria Alba (150cm - 240cm ht) Each ——_ ))Pulmeria Rubra (150cm - 240cm ht) cach— 100.00 ₹1,500 — — not billed / not read medium [1]
ntia Palm) (SOcm-60cm ht tach _ - ro _3__ Roystonia Regia (180cm - 240cm ht) . tach _ % ~~— 74.00 ₹2,000 — — not billed / not read medium [1]
bearings maintenance a “free ball bearings -scope of delivery completely pressed assembled— 1.00 ₹1,44,800 — — not billed / not read medium [1]
m the spot, a Including lead, lift loading and unloading charges.(1x1x0.15m)as directed by— 4,000.00 ₹35 — — not billed / not read medium [1]
ty 2persons \ a a a es ee cc case ___ cst % a a a ee a cae? Saas et ee ee Each____—_— ._—@— 1.00 ₹1,25,600 — — not billed / not read medium [1]
: __4 __ Caryota Urens (240cm - 300cm ht YEach ~ =— 50.00 ₹2,500 — — not billed / not read medium [1]
uble-LK-SL- )All round and rectangular pipes are GI or CRISI make.Gauge . ( .Q0 Each @ ( P— 23.00 ₹5,310 — — not billed / not read medium [1]
es - x of pits and trenches, dking the excavated soil clear from edges of excavation Cum .cum 373.45 ₹306 — — not billed / not read high [1]
- _ et — , i For Center theme Cum) .95_ se gl os — i — Cum ) — . . a Cum ) = Pum sid rota— 373.45 ₹306 — — not billed / not read medium [1]
ected by the engineer Inchargeof the work ; ; Cost of the plant ( Plants per Sq.m) ‘ , , asqm 1,500.00 ₹75 — — not billed / not read high [1]
thed, galvanized, steel strip confirming to IS- : (No of Strip indicated in GTP) & mtr . *m 750.00 ₹119 — — not billed / not read high [1]
in courses not fess than cms high, bond stones at two m. apart In each course cum Lae ~*~cum 14.63 ₹5,305 — — not billed / not read high [1]
concrete i jlaid In layers not exceeding cms. thick, well compacted, in foundation and ot.— 12.73 ₹5,159 — — not billed / not read medium [1]
suitable for working voltage upto 1100Volts as per !S- : & confirming to GTP of GROUP- '.— 760.00 ₹82 — — not billed / not read medium [1]
65x65 Basic rate - : — ‘ . : i = Area weightage % , - ° : ot Total ee _ : - —— = - oO sqmsqm 47.61 ₹1,273 — — not billed / not read high [1]
ng to the adjoining wat members wherever necessary complete as per design (laps, hooks and— 9.32 ₹6,368 — — not billed / not read medium [1]

Running-bill figures show progress at that bill, not final quantities. Comparisons are inferred; see methodology.

Timeline

  1. 28 Dec 2017 Tender BBMP/2017-18/OW/WORK_INDENT27988 published inferred source
  2. 11 Apr 2019 Final bill ₹2.32 Cr paid source

Tender notices

Tender no.SourcePublishedStatusEstimateAwardedToTime allowedLinkEvidence
BBMP/2017-18/OW/WORK_INDENT27988BBMP list28 Dec 2017Tender published (outcome not in this list) ——— —high record · row 4253

Bills & payments (BBMP)

Bill typeBill reg. (BR)Work orderGrossNettPaymentPayeeSource
Final 000138 · 19 Mar 2019 — ₹2,31,94,865₹2,18,95,735 RTGS 000014 11 Apr 2019 Billapur Yellappa Perumaiah BBMP IFMS payment grid (all paid work bills, mid-2015 onward) · row None

Original system: BBMP Works Bill Public View / IFMS (account.bbmpgov.in). Linked files are public exports of that data on OpenCity.

Why this is a Koramangala project

Work description names Koramangala: "…Development of park at south zone Koramangala ward No 151 south zone…"