Buildings & civic facilities · job 148-17-000052
Constrcution of office Building in NGV ward No.148 (Ejipura)
—contract / award · unknown
₹30.92 Lpaid, gross
1bills
08 Jul 2021last activity
- Planned
- Contracted
- Work documented
- Paid
- Completed
- Physical evidence
no tender found for these bills
Signals — patterns worth a closer look, not findings of wrongdoing
-
info Median 771 days from bill registration to payment confirmed
Long payment delays are common (seniority-based bill clearance) and raise contractors' financing costs. [source]
-
info Bill paid 2 years after work end date confirmed
Long payment lag; common with BBMP bill backlogs (seniority-based payment). [source]
1 · What was planned
Work
Where
NGV; Ejipura
inferred
Place names read from the work description text
Ward
Estimated cost
Unknown
unknown
No estimate published for this work in the sources used
Tender published
Unknown
unknown
No tender found or matched for this work
Time allowed
Unknown
unknown
No tender document found or matched
2 · Who got the work (contract)
Contractor
Contractor identity
C0107 · Sri. N Narasimha
inferred [1]
Resolved contractor C0107 “Sri. N Narasimha”; identifiers: no official identifier in the data; name variants joined by: same / truncated name ×1. Also appears as: N Narasimha.
Contract value
Unknown
unknown
Contract (work-order) value is not published in BBMP bill data and no awarded tender was matched
Work order date
3 · Work documented
Bills recorded
0 running, 1 final paid/registered
confirmed [1]
Bill types recorded in BBMP IFMS for this job's work bills
4 · Money paid
Paid (gross)
Paid (nett)
Bills
First payment
Last payment
Bill → payment (median days)
Approval remarks
9 remark(s); e.g. 2021-07-06: “Forwarded — Verified with bill form as per the Commissioner Order No CAO/PR/ 4415/15-16 dated 05-05-2016 and CAO Inter Office Memo No CAO/PR/5272/15-16 dated 26”
confirmed [1]
Remarks written by officials in the IFMS approval chain
5 · Completion
Status
Completed (final bill)
inferred [1]
Inferred from the final bill: BBMP raises the final bill when measurement of the completed work is recorded
Work started
Expected completion
Unknown
unknown
Stipulated period of completion not found in any public record
Final bill
Completed on
6 · Physical evidence
Timeline
Bills & payments (BBMP)
| Bill type | Bill reg. (BR) | Work order | Gross | Nett | Payment | Payee | Source |
|---|---|---|---|---|---|---|---|
| First and Final | 000041 · 29 May 2019 | 000429 12 Feb 2019 | ₹30,91,924 | ₹27,97,186 | 08 Jul 2021 | Sri. N Narasimha | BBMP Work Orders - Ejipura (Ward 148), 2013-2022 · row 89 |
Original system: BBMP Works Bill Public View / IFMS (account.bbmpgov.in). Linked files are public exports of that data on OpenCity.
Why this is a Koramangala project
Work description names Koramangala: "…Constrcution of office Building in NGV ward No.148 (Ejipura)…"