Case file · KP6-304-17-000105
timeline follow-upPast completion date, no final bill
Project
Construction of Elevated corridor by integrating Ejipura main road-Inner Ring Road junction, Sony World junction and Kendriya Sadana junction along 100ft. Inner Ring Road, Koramangala, Bangalore.
Job 304-17-000105 · Junctions, flyovers & grade separators · Ejipura; Inner Ring Road · Bruhat Bengaluru Mahanagara Palike
Contractor: M/s Simplex Infrastructures Limited · paid to, per IFMS bills: M/s Simplex Infrastructures Limited ₹95.40 Cr (2017-06-21 → 2021-09-28); INFRA SUPPORT ENGGCO ₹68.76 L (2019-07-09 → 2021-09-30); M RAMESH ₹3.79 Cr (2022-04-21 → 2022-04-21); ESCROW A/C BSCPL INFRASTRUCTURE LTD ₹60.79 Cr (2024-01-24 → 2025-07-01)
What was promised
- Contract / work-order value
- ₹176.11 Cr (inferred)
- Estimate
- ₹157.66 Cr
- Work order
- EE (PC-9)/WO/ 03/2023-24 dated 2023-11-15
- Stipulated completion
- 14 Feb 2025
What happened
- Paid (gross / net)
- ₹160.67 Cr / ₹121.11 Cr
- Bills
- 25 · 21 Jun 2017 → 01 Jul 2025
- Final bill
- none recorded
- Status
- Running bill only (no final bill found)
- Extensions of time
- 2 extension-of-time order(s): to 2020-12-31 (423 days), fine ₹4,879,134; to 2021-12-31 (365 days), fine ₹10,900,000
- Pending bills
- 5 bill(s) not paid (₹150,249,142); at: AE ×3, SC(F) / CE ×1, Executive Engineer ×1
- Deductions
- fine ₹3,100,000; mobilizationadvance ₹189,655,010
Why this case deserves follow-up
Past completion date, no final bill (unexplained in public record, high confidence)
Stipulated completion was 2025-02-14; extension-of-time orders in IFMS: 2019-11-04 → 2020-12-31 (423 days), penalty ₹48.8 L; 2020-12-31 → 2021-12-31 (365 days), penalty ₹1.09 Cr. These cover an earlier period; none is visible for 2025-02-14. As of 2026-10-07, 600 days have passed since 2025-02-14; no final bill is recorded and the last payment was on 2025-07-01. Pending bills: 5 bill(s) not paid (₹150,249,142); at: AE ×3, SC(F) / CE ×1, Executive Engineer ×1. Penalties stated in the EoT orders total ₹1.58 Cr; IFMS deductions labelled 'fine' total ₹31.0 L.
Possible legitimate explanations
- An extension of time was granted but not uploaded.
- Work is complete and the final bill is pending approval.
- Scope was re-packaged into another contract or job.
What would resolve it
- EoT order for the current contract
- Penalty / liquidated-damages calculation
- Current progress report
Questions an investigator could ask
- Has an extension of time been granted for job 304-17-000105 beyond 2025-02-14? If so, provide the order.
- What liquidated damages / penalties have been calculated and recovered, bill by bill?
- What is the current physical progress and the expected completion date?
- Why are the pending bills held, and at which approval level?
Specific records to request (RTI)
- Extension-of-time order(s) for the current contract and the penalty calculation — job 304-17-000105; stipulated completion 2025-02-14. Why: No EoT for this date is attached in IFMS.
- Statement of fines / liquidated damages levied and recovered, bill by bill — job 304-17-000105; EoT orders levy ₹1.58 Cr; IFMS shows ₹31.0 L deducted as fine. Why: Reconciles penalties ordered with penalties recovered.
Evidence
- Work Order: WO-7--50043841-WORK ORDER.pdf (page 2)
· document · confidence inferred
printed / OCR text
OCR: “n 15 Months 5 Date of Commencement of Worle 15.11.2023 6. Date of Completion 14.02.2025 7. Government Approval No No UDD 316 MN” - IFMS attachment WB-Ot--03006023-EOT (1).pdf, p.1
· document · confidence inferred
printed / OCR text
its allied activities. The extension of time is accorded | from 4/11/2019 to 31/12/2020 (423 days) with a penalty of Rs 48,79,134.00 (Rupees Forty | eight lakhs seventy nine thousand one hundred and thirty f - IFMS attachment WB-Ot--04913968-EOT.pdf, p.1
· document · confidence inferred
printed / OCR text
its allied activities. The extension of time is accorded | from 31/12/2020 to 31/12/2021 (365 days) with a nominal fine of Rs 1.09 crore considering | the delay in the casting of the segments at the casting y - BBMP IFMS work bill 350792
· api · confidence confirmed
printed / OCR text
Pending bill - BBMP IFMS work bill 350793
· api · confidence confirmed
printed / OCR text
Pending bill - BBMP IFMS work bill 706850
· api · confidence confirmed
printed / OCR text
Pending bill - BBMP IFMS work bill 337757
· api · confidence confirmed
printed / OCR text
Deductions - BBMP IFMS work bill 250089
· api · confidence confirmed
printed / OCR text
Deductions - BBMP IFMS work bill 366821
· api · confidence confirmed
printed / OCR text
Deductions - EoT order WB-Ot--03006023-EOT (1).pdf · p.1
· document · OCR (tesseract psm 6, 2x) · confidence medium, cross-validated
printed / OCR text
its allied activities. The extension of time is accorded | from 4/11/2019 to 31/12/2020 (423 days) with a penalty of Rs 48,79,134.00 (Rupees Forty | eight lakhs seventy nine thousand one hundred and thirty f - EoT order WB-Ot--04913968-EOT.pdf · p.1
· document · OCR (tesseract psm 6, 2x) · confidence medium, cross-validated
printed / OCR text
its allied activities. The extension of time is accorded | from 31/12/2020 to 31/12/2021 (365 days) with a nominal fine of Rs 1.09 crore considering | the delay in the casting of the segments at the casting y
IFMS work bills for this job: 89957, 180520, 201529, 216261, 230383, 238995, 250089, 260487, 266871, 282470, 315583, 321936, 337757, 350790, 350792, 350793, 350794, 350795, 366821, 446228
Investigation lead, not an accusation. Every statement on this page is generated from the published case data (JSON).